 Nov. 16, 2026
|
|
The first phase of construction in the Weld County Road (WCR) 66 project will occur between the Union Pacific Railroad tracks at U.S. 85 to Sand Creek, crossing just east of WCR 43.
Early work, starting later this year, will focus on moving irrigation lines out of the right-of-way so they can continue operating in the spring. Municipal waterlines and other public utilities will also be relocated.
Ahead of this, however, the project management and contracting teams are working on several tasks. They include:
- Refining the project’s design plans, which are 60% complete.
- Working with Weld County to finalize irrigation agreements with property owners.
- Reviewing utility location information gathered during last month’s potholing work.
- Developing cost estimates and agreements for relocating utilities.
- Refining driveway designs where needed to ensure they drain properly, have adequate sight lines, and tie directly into ditches along WCR 66.
- Drafting quality control plans, specifications and determining quantities.
- Compiling a construction cost package for this first phase of work and submitting it to Weld County this month.
Pictured above: An irrigation ditch and field sit beside WCR 66. Early construction will focus on the west end of the corridor between U.S. 85 and Sand Creek, crossing just east of WCR 43.
|
|
|
|
Have questions about the project or need to speak with a project team member? Reach out via email at wcr66@weld.gov or by calling the project hotline at (970) 620-9590.
More information on this project, including past newsletter updates, can be found on www.weld.gov/Go/WCR66.
|
|
|
|