June 5, 2025 | 12:45 p.m.
Greetings,
The delivery of a large pipe section for Yuba Water Agency’s Colgate Tunnel and penstock improvement project will now arrive later than anticipated, likely early afternoon tomorrow, Friday, June 6. As a reminder, traffic along Marysville Road, Old Dobbins Road and Lake Francis Road will be impacted during the delivery.
Here’s what you need to know:
- The delivery will be traveling eastbound on Marysville Road and is expected to reach Lake Francis Road early afternoon.
- This is an approximately 19-foot tall, 16-foot-wide, oversized load that will be escorted by the California Highway Patrol to ensure safety and manage traffic. Local utilities will also be on-site to help move any utility lines along the route.
- Traffic control will allow vehicles to pass through, but expect some delays, especially along narrower sections of Lake Francis Road where turnouts are limited. Allow extra time to travel in and out of the area in the afternoon.
Due to the size and complexity of this delivery, the exact schedule may change again depending on road conditions and other logistics. We’ll plan to reach out again early Friday to share a more defined delivery window.
For more information and to stay connected, visit engage.yubawater.org/colgate-tunnel or contact us at communications@yubawater.org.
Thank you, Yuba Water Agency’s Public Information Team
|
|
|
The June 6 penstock pipe sections delivery will be traveling eastbound along Marysville Road toward New Colgate Powerhouse. The delivery is now expected to reach Lake Francis Road in the afternoon.
|
|
|
|