Overnight work will resume on Sunday, November 23rd between the hours of 8PM - 5AM. The project experienced unexpected delays due to weather and a delay in receipt of materials. Weather permitting, the project timeline is:
November 23 - 25 and November 30
- Overnight Work: Paving along Laurel and placement of visible lane markers along Laurel while the striping work is pending.
December 2025
- Day work: Manhole adjustments and residential street work on connecting side streets.
- Overnight Work: Striping.
January 7, 2026
- Projected project completion date.
Regular updates will be provided as available.
|
|
Los trabajos nocturnos se reanudarán el domingo, 23 de noviembre, entre las 8:00 p.m. y las 5:00 a.m. El proyecto experimentó retrasos inesperados debido al clima y a la demora en la recepción de materiales. Sujeto a condiciones climáticas, el calendario del proyecto es el siguiente:
23 al 25 de noviembre y 30 de noviembre
- Trabajo nocturno: Pavimentación a lo largo de Laurel y colocación de marcadores de carril visibles a lo largo de Laurel mientras el trabajo de marcado de líneas está pendiente.
Diciembre de 2025
- Trabajo durante el día: Ajustes de pozos de registro (alcantarillas) y trabajo en calles residenciales conectadas.
- Trabajo nocturno: Demarcación (rayado) de carriles.
7 de enero de 2026
- Fecha proyectada de finalización del proyecto.
Se darán actualizaciones regulares a medida que estén disponibles.
|
|
|
|