A.  Scope of Work: Phase 3

 

  1. Surveying, layout and construction staking;
  2. Marking and potholing underground utilities;
  3. Place low level barricades with flashing beacons and K-rail;
  4. Removal of pavement striping and markings;
  5. Removal of airfield lighting, cables, light cans and conduits;
  6. Installation of new light cans and conduits;
  7. Cold mill pavement and transport grindings off site;
  8. Placement of new base repair and asphalt pavement;
  9. Installation of new airfield lighting and miscellaneous electrical  work;
  10. Rout and seal pavement cracks;
  11. Placement of pavement rejuvenator and sealer;
  12. Striping and pavement marking;
  13. Installation of pavement markers;
  14. Installation of taxiway edge reflectors. 

 

 B.  Duration of Project and Planned Schedule:

50 calendar days – December 5, 2011 to January 23, 2012

 Work hours:   Day-time: 0700 to1600

         Night-time: 1600 to 2400

         Graveyard: Mon 0001 to 0600   

                    

 C.  Location of Work and Route:

Location: Taxiway W between Taxiways U and V

     (see attached location map)                 

Routes to access worksite will be:

  •  Gate B (limited to non trucking traffic)
  •  Air Cargo Way to Aircraft Rescue Fire Fighter (ARFF) Station Gate.

 

D.  Storage Site:    

Storage area will be the closed portion of Txln W and B and paved apron area at the OMC or as designated by Port.

 

EVehicles:

Construction vehicles will display the appropriate placards, orange and white checkered flags during day light operations and flashing beacons during night time operations.

 Vehicles will at all times comply with Oakland International Airport, Airport Operations Area (AOA) Vehicle Safety Rules 406.2.

 

 F.  Personnel Identification: 

Personnel will be properly badged or under escort into the security zone by properly badged contractor (Gallagher & Burk and their subcontractors) personnel, Airport Construction personnel and/or Airport Operations personnel.

           

G.  Special Instructions and/or Restrictions

 Restrictions during construction:

1. Truck and equipment access will be through ARFF gates.

2. Truck haul routes shall be restricted as showin in the plans

3. During continuous trucking of materials, contractor shall provide a pilot car to  escort trucks hauling materials to and from the AOA.

4. Where trucks will cross active taxiways, contractor shall provide a flagger who will be in contact with ATCT and will direct traffic accordingly.

5. Closure of any taxiways or taxilanes will be published via NOTAM.

6. Txwy W between Txwys U and V will be closed; Txwy B between GRE and Txwy W will be closed; access to GRE from Txwy T will be maintained.

7. Trucks will cross active Txwy V ina ccordance with Restriction 4 above.

8. Other restrictions as specificed in SEC. 01560 of the project manual            

 Contractor’s representative will be present at the work site or be available by telephone at all times that work is in progress.

 Work site and trucking route are to be kept clean and free of debris.    Prior to leaving the worksite, Airside Operations Supervisor must be notified for an inspection of the area.

 All trench work must be barricaded off or covered at the end of each work day.

 Each work area will be barricaded off with low level barricades.

 Low level barricades and flashing beacons will mark the area under construction.

During trucking operations access gates will be guarded when open by ABC Security during working hours.

HPort Principal Personnel: (Telephone Numbers)

Resident Engineer (RE):  Eleazar Academia  

Contact: 510-466-7867

Cell: 510-773-9976

Fax: 510-466-7813

Radio Call Sign: AP111

 

Airside Operations PM: James E Trickel, Airside Operations Supervisor / MOD

Contact: 510-563-6438

Cell: 510-715-8419

 

Contractor: GALLAGHER & BURK, INC.

Project Manager: Dave Thompson      

Contact: 510-261-0466

Cell: 925-785-8627

Project Engineer: Jared Cushman

Contact: 510-261-3806

Cell: 510-914-4488

Radio Call Sign: Gallagher 1

Superintendent: Ed Rosa

Contact: 510-913-4488

Radio Call Sign: Gallagher 2

Superintendent, Nick Scruggs, Columbia Electric

Contact: 925-719-2959

Radio Call Sign: Columbia1


 

 

 

 

 

 

You are subscribed to Airport Bulletin for Port of Oakland, California. This information has recently been updated, and is now available.