Pomona to Claremont A Line Extension Updates

The project design team, Parsons, was active along the project corridor this past month conducting surveying and geotechnical investigations. As shared over the past few months, the survey work is underway to capture critical data on existing utilities, drainage, track slope elevations and other site conditions; while the geotechnical borings provide a better understanding of the soil conditions under the project corridor and at future light rail bridge locations. Together, this data gives the design team a clearer picture of existing conditions and provides the foundation needed to advance the design with confidence.

With these field investigations nearing completion, the project remains on schedule to reach the 60% design milestone in early January 2027. The 60% design package is a critical step in preparing the project for construction. By this stage, the major elements of the project, including track infrastructure, civil improvements, utilities, structures, stations, and related systems, will be defined and coordinated as part of a comprehensive design package. As the project advances through the 85% and 100% design phases, these elements will be further refined and detailed before the plans reach the "Approved for Construction" stage late next year.

1121314

Crews conducting surveying (top two photos) and geotechnical borings (bottom two photos) along the project corridor and at future light rail bridge location in October

As design work continues, the project contractor - SSH JV - is providing vital support. Working alongside the Construction Authority, SSH JV is identifying opportunities to reduce construction risk and costs, improve efficiency for the project as they develop an overall construction schedule, prepare programmatic plans, conduct field reviews and recommend early work packages that can help keep the project on track.

Looking ahead, SSH JV will have the opportunity to negotiate a construction contract to build the Pomona to Claremont A Line Extension with a guaranteed maximum price once the design reaches 85%; expected next Fall. Major construction is expected to begin in late-2027 and take approximately four years.


Hundreds Stop by Foothill Gold Line Booth at Claremont’s Village Venture

VV11VV2

Thank you to everyone that stopped by the Foothill Gold Line booth this past Saturday, October 24, at Claremont’s 44th Annual Village Venture Arts & Crafts Festival. Our team had the opportunity to connect with hundreds of community members from throughout the project corridor and beyond, sharing the latest updates on the project, and answering many questions about the Pomona to Claremont A Line Extension. We also enjoyed sharing information on how to ride the Metro system and all of the great places to explore utilizing the County’s rail network.

It was a great day, as always, to be in Claremont and our team looks forward to participating at future events where we can update the community on the progress being made to extend the Metro A Line to Claremont.


Join Us at a Community Open House on Tuesday, December 1 from 5:30 PM – 7:30 PM

The Construction Authority is hosting a Community Open House on Tuesday, December 1st to provide the latest information on the Pomona to Claremont A Line Extension; give the community an opportunity to meet the project team and Claremont Station artist, Joyce Kohl; and to answer questions. We hope you will join us at the Alexander Hughes Community Center between 5:30 PM - 7:30 PM. Arrive anytime, there is no formal presentation.

ad

Thank you for your interest in the Foothill Gold Line.

Lisa Levy Buch, Chief Communications and Strategic Development Officer and the Public Affairs Team

Bookmark and Share

E-News Content

Pomona to Claremont A Line Extension Updates

Foothill Gold Line at Village Venture

Join us at the December 1st Community Open House 


Foothill Gold Line Construction Authority Headquarters
404 E. Huntington Drive
Second Floor
Monrovia, CA 91016

Phone: (626) 471-9050

Office Hours: Mon - Thurs, 9 AM - 4 PM

Mailing Address
406 E. Huntington Drive
Suite 202
Monrovia, CA 91016

 

===============

 

PROJECT  FUNDING:

Project funding for the Pomona to Claremont A Line Extension is mostly coming from LA Metro from a state grant funded by SB125. 

 

===============

 

QUESTIONS ABOUT METRO A LINE SERVICE (INCLUDING TRAIN SCHEDULES, FARES, PARKING, DISCOUNTS, ETC) SHOULD BE DIRECTED TO METRO:

Metro Customer Service can be reached at 1-323-466-3876 (1-323-Go Metro)
or customerrelations@metro.net