Foothill Gold Line E-News Update – MILESTONE REACHED: Major Work Completed on New Light Rail Track System

Having trouble viewing this email? View it as a Web page.

Header Oranges

E-NEWS UPDATE

June 26, 2023

Milestone Reached: Completion of Major Work on New Light Rail Track System from Glendora to Pomona

1

Photo: Foothill Gold Line board members with elected regional leaders and KPJV track crew members after rail clip was installed on Saturday.

This past Saturday, the Construction Authority held a Track Completion Ceremony to celebrate the completion of major work for the new light rail track system for the 9.1-mile, four-station Foothill Gold Line light rail project from Glendora to Pomona. The celebration took place at the D Street railroad crossing in La Verne, just steps away from the University of La Verne, the County Fairplex and the future La Verne station. The event culminated in the installation of the 230,630th rail clip (rail clips permanently attach the steel rail to the concrete railroad ties), officially completing major construction for the new light rail tracks, and permanently connecting the cities of Glendora, San Dimas, La Verne and Pomona via this new light rail line. An engraved, commemorative boulder to be permanently embedded in the sidewalk was also unveiled during the ceremony, recognizing the importance of the day to these corridor cities.

The project is now 72% complete overall and remains on schedule to reach substantial completion in early-January 2025, when it will be turned over to Metro for training and pre-revenue service. Metro determines when passenger service starts.

1

Photo: About 400 community members, project stakeholders and elected officials during the Track Completion Ceremony.

Saturday's historic event was attended by about 400 community members, elected officials at all levels of government, the Foothill Gold Line Board of Directors, members of the Los Angeles County Metropolitan Transportation Authority (Metro) Board of Directors, transportation officials – including Foothill Gold Line CEO Habib F. Balian and Metro CEO Stephanie Wiggins – and San Gabriel Valley stakeholders.

Below is a video recap and photo gallery of the ceremony, as well as media coverage.

Video Recap

Click here or below to watch.

11

Photo Gallery

To see the full gallery, click here.

111111111111111

Media Coverage of Track Completion Ceremony

Below are links to TV, print and blog media coverage of the historic milestone achievement:

TV Segment: KCAL 9
https://youtu.be/t7uG1F1XdUU

TV Segment: CBS 2
https://youtu.be/ZXgk3mQK9KY

TV Segment: ABC 7
https://youtu.be/xRXI-jqqK7o

TV Segment: NBC 4
https://youtu.be/COHD6RONmCM

TV Segment: Telemundo
https://youtu.be/ZLjGvX_4ghM

San Gabriel Valley Tribune/Inland Valley Daily Bulletin: Light-rail track from Glendora to Pomona completed, as project moves closer to opening
https://www.sgvtribune.com/2023/06/24/light-rail-track-from-glendora-to-pomona-completed-as-project-moves-closer-to-opening/

Progressive Railroading: Foothill Gold Line authority wraps up light-rail track construction
https://www.progressiverailroading.com/passenger_rail/news/Foothill-Gold-Line-authority-wraps-up-light-rail-track-construction--69542

Mass Transit Magazine: Foothill Gold Line celebrates completion of major trackwork for Glendora to Pomona light-rail project
https://www.masstransitmag.com/rail/infrastructure/press-release/53064393/metro-gold-line-foothill-extension-construction-authority-foothill-gold-line-celebrates-completion-of-major-trackwork-for-glendora-to-pomona-lightrail-project

Urbanize LA: Track work completed for Foothill Gold Line extension to Pomona
https://la.urbanize.city/post/track-work-completed-foothill-gold-line-extension-pomona

Streetsblog LA: Regional Connector Opens and Track Construction Finishes on the Gold Line
https://la.streetsblog.org/2023/06/22/sgv-connect-113-regional-connector-opens-and-track-construction-finishes-on-the-gold-line

Pasadena Now: Foothill Gold Line Commemorates Completion of Major Rail Work in Historic Ceremony
https://www.pasadenanow.com/main/foothill-gold-line-commemorates-completion-of-major-rail-work-in-historic-ceremony

Metro Magazine: Foothill Gold Line Celebrates Completion of Work for New Light Rail Track System
https://www.metro-magazine.com/10201351/foothill-gold-line-celebrates-completion-of-work-for-new-light-rail-track-system


Thank you for your continued interest in the Foothill Gold Line. We appreciate your patience as we build this important regional project.

Lisa Levy Buch, Chief Communications and Strategic Development Officer and the Public Affairs Team

E-News Content

Milestone Reached: Completion of Major Work on New Light Rail Track System from Glendora to Pomona

Video Recap and Photo Gallery of Track Completion Ceremony

Media Coverage of Track Completion Ceremony


STAY UPDATED OR GET QUESTIONS ANSWERED

Access Project information 24/7 at foothillgoldline.org.

For Construction-Related Questions:
(626) 513-5788
CommunityRelations@Kiewit-Parsons.com

For General Project Questions:
(626) 471-9050
publicaffairs@foothillgoldline.org

 

===============

 

Foothill Gold Line Construction Authority Headquarters
406 E. Huntington Drive
Suite 202
Monrovia, CA 91016

Phone: (626) 471-9050

Office Hours: Mon - Thurs, 9 AM - 4 PM

 

Construction Public Information Office
2100 E. Route 66
Suite 200
Glendora, CA 91740

Office Hours: Mon - Fri, 8 AM - 4 PM

 

===============

 

PROJECT  FUNDING:

Project funding in Los Angeles County is mostly from Measure M; with additional funding from Measure R and the State of California Transit and Intercity Rail Capital Program (including funds from SB1).

San Bernardino County funds will be used to extend the line from Claremont to Montclair (with TIRCP and SB1 funds).

 

===============

 

QUESTIONS ABOUT GOLD LINE SERVICE (INCLUDING TRAIN SCHEDULES, FARES, PARKING, DISCOUNTS, ETC) SHOULD BE DIRECTED TO METRO:

Metro Customer Service can be reached at 1-323-466-3876 (1-323-Go Metro)
or customerrelations@metro.net