As part of the ongoing effort to ready the
Glendora to Montclair segment for construction, crews have recently been
conducting tests at key locations along the
alignment to evaluate soil conditions. In the photos below, crews are shown
collecting soil data by drilling 100-foot deep borings in Glendora at the
intersection of Grand Avenue and Foothill Boulevard (top) and at Lone Hill
Avenue (bottom). These sites are two of the two dozen locations along the
future alignment where bridge structures will likely be built or renovated.
 Soil sample collection at intersection of Grand Avenue and Foothill Boulevard, Glendora
 Soil sample collection at Lone Hill Avenue, Glendora
 On the one year anniversary of the opening of the Gold Line from
Pasadena to Azusa, Bike SGV and Los Angeles County Metro will be hosting 626
Golden Streets, an open streets event spanning seven cities in the San
Gabriel Valley where more than 17 miles of roadways will be closed off from
automobiles to allow for people to walk, bike, jog, skate and more. The route,
taking place between South Pasadena and Azusa, will connect with the newest Gold Line stations in Arcadia, Monrovia, Duarte, Irwindale and
Azusa.
Foothill Gold Line staff
will be hosting a booth near the Azusa Downtown station. Stop by and say hi or to ask any
questions you may have about the Glendora to Montclair extension.
626 Golden Streets takes place on Sunday, March 5, 2017, from 9 AM to 3 PM. For more information on the event, including the route, visit www.626goldenstreets.com.
|