Below are the most recent updates on the situation with the Hyperion Water Reclamation Plant.
- Bill AB-1216 Wastewater Treatment Plants: Monitoring of Air Pollutants:
- City staff and councilmembers have been working tirelessly with Assemblymember Al Muratsuchi's office and various stakeholders on bill AB 1216.
- Bill AB 1216 is tentatively scheduled to be heard at the Senate Appropriations Committee Hearing on Monday, August 14, 2023.
- Track the bill's most recent language and status here.
- Hyperion Activity
- Tank Cover Measurement Activity - Starting July 17 until July 28, 2023, on weekdays between 7:00 a.m. - 5:00 p.m. there will be tank measurement activities of Primary Battery D. The work may release some odor.
- Perimeter Road Project - is 95% complete and is expected to be fully completed by the end of August 2023. A forecast of remaining construction, with anticipated completion dates can be found here.
- Dr. Michael K. Stenstrom, Wastewater Treatment Plant Expert, continues to track Hyperion's progress implementing the 33 recommendations from the Hyperion Ad Hoc Committee formed after the July 2021 spill and is scheduling a tour of Hyperion for himself and the Environmental Committee.
- The Hyperion Ad Hoc Committee comprised of Councilmember Carol Pirsztuk, Councilmember Ryan Baldino, and Environmental Committee Chair Tracey Miller-Zarneke continue to meet with the City Manager weekly.
Tank Cover Measurement Activity July 17 - July 28, 2023
Starting July 17 until July 28, 2023, Hyperion will be conducting measurement activities of Primary Battery D. The measurements are needed for the fabrication of new covers for the tanks. Work hours will be limited between 7:00 a.m. and 5:00 p.m. during weekdays.
During the work, old covers will be lifted up for the accurate measurements which may release some odor. In order to reduce the odor nuisance, only one cover will be removed at a time, and the cover will be installed back immediately after necessary measurements are taken.
If you have any questions, please feel free to email the Community Outreach Team at LASAN.CleanWater.Outreach@lacity.org.
|
|