City of Culver City sent this bulletin at 10/18/2024 02:16 PM PDT
MOVE 2.0
Construction
Continues
This Week (Week of October 14)
Crews continued applying blue, green, and red-colored pavement markings.
Crews began replacing signage throughout the corridor.
Contractors began repairing bus/bike platforms to prepare for installation in the Arts District.
Next Week (Week of October 21)
Crews will begin to install horizontal and vertical delineators in the bus/bike lane and at curb extensions.
Crews will continue to apply colored pavement markings.
Crews will continue to replace signs.
Detours and Construction Impacts
The City is working to minimize dust, noise, and temporary lane closures throughout construction. However, some level of construction impacts are anticipated to occur.
Remember: Bikes May Use Full Lane. Please remember to share the road and give bikes three feet when passing.
Bikes may use the travel lane at all times. Bikes may also use Venice, Braddock, Lucerne, the Expo Bike Path, and the Ballona Creek Bike Path to navigate around the construction area.
One lane of traffic in each direction will be maintained at all times.
Businesses will remain open, and access will be provided during normal business hours.
Construction crews are using street sweepers and other measures to minimize dust when possible.
For safety, please observe all posted traffic controls, parking restrictions, and detours.
Bus Detours began on September 5th, and will continue through the end of construction. The detour affects Culver CityBus Lines 1, 1C1, 5, and 7, LADOT CE437A, Big Blue Bus Route 17, and Metro Line 617. These routes will run along Venice Boulevard instead of along the MOVE Corridor. Detours will be maintained throughout the construction period to provide a consistent experience for riders.