Construction
Continues
This Week
Crews completed removal of existing striping.
Resurfacing work is complete between Washington Blvd./Ince Blvd. and Washington Blvd./Robertson Blvd. /Higuera St.
Contractors worked with City inspectors to lay out new road markings in advance of installation.
Next Week
Crews will apply the updated markings to the roadway.
Crews will be removing and relocating signage according to the modified design.
Work is proceeding on schedule and substantial completion is expected by the end of October.
Image below provides an overview of the new roadway configuration.
Detours and Construction Impacts
The City is working to minimize dust, noise, and temporary lane closures throughout construction. However, some level of construction impacts are anticipated to occur.
Remember: Bikes May Use Full Lane. Please remember to share the road and give bikes three feet when passing.
One lane of traffic in each direction will be maintained at all times.
Businesses will remain open, and access will be provided during normal business hours.
Construction crews are using street sweepers and other measures to minimize dust when possible.
For safety, please observe all posted traffic controls, parking restrictions, and detours.
Bus Detours began on September 5th, and will continue through the end of construction. The detour affects Culver CityBus Lines 1, 1C1, 5, and 7, LADOT CE437A, Big Blue Bus Route 17, and Metro Line 617. These routes will run along Venice Boulevard instead of along the MOVE Corridor. Detours will be maintained throughout the construction period to provide a consistent experience for riders.