UPDATE: Final paving on SR 89 on White Spar Road in Prescott next week
Arizona Department of Transportation sent this bulletin at 06/11/2014 04:19 PM MST. If you would like alerts on this and other ADOT news, sign up above to receive our GovDelivery notices.UPDATE: Final paving on SR 89 on White Spar Road in Prescott next week
Crews will apply the final layer of asphalt Monday and Tuesday
The final layer of pavement will be placed on State Route 89 (White Spar Road) in Prescott on Monday and Tuesday, June 16 and 17 between 6 a.m. and 6 p.m. each day.
This paving work did not occur earlier this month as originally publicized.
Drivers can expect delays of up to 15 minutes during paving activity. Once paving work is done, the project will be substantially complete with the exception of the final striping which will occur 30 days from now.
The speed limit will be reduced to 25 mph through the work zone. ADOT advises drivers and bicyclists to proceed through the work zone with caution, comply with the reduced speed limit and be alert for construction equipment and personnel.
For more information, email projects@azdot.gov or call the ADOT Project Hotline at 1.855.712.8530. To stay up-to-date with the latest highway conditions around the state, visit the ADOT Traveler Information Center at www.az511.gov or call 511.