UPDATE: Interstate 40 at Anvil Rock Road closed overnight for bridge deck demolition June 15-17

NOTE REGARDING UPDATE: Full closure dates have been moved to June 15-17

The Arizona Department of Transportation advises drivers to plan for full overnight closures of Interstate 40 at Anvil Rock Road as work continues on the  Anvil Rock Road Bridge rehabilitation project.

The full closure of I-40, approximately 11 miles west of Seligman, will occur overnight from 8 p.m. to 6 a.m. beginning Wednesday night, June 15, and ending Friday morning, June 17. 

  • East- and westbound I-40 will be closed in each direction at Anvil Rock Road to allow for the demolition of the Anvil Rock Bridge over I-40. 
  • Motorists will use the Anvil Rock Road off- and on-ramps to exit and re-enter the interstate. The speed limit will be reduced in the work zone.  

The $2.7 million project includes the removal and replacement of the existing bridge deck, which is the top surface of the bridge that motorists drive on, as well as the approach slabs, guardrail and pavement markings.

For more information on this project, visit I-40 Anvil Rock Road Bridge Deck