 MARANA
‒ The Arizona Department of Transportation is moving toward the next phase of
creating a modern Ina Road interchange with Interstate 10 in the growing
community of Marana northwest of Tucson.
The
project, with a total construction cost of $148 million, will relieve traffic
congestion by widening I-10 and by carrying a widened Ina Road over Union
Pacific tracks that carry between 40 and 60 trains a day.
“When
we complete this project, this area will be better for drivers because they no
longer will need to wait for trains or cross the tracks on their way to work,”
said Rod Lane, district engineer for the Arizona Department of Transportation’s
South Central District. “The added lanes on both Ina Road and I-10 should allow
traffic to move through the area more efficiently.”
Last
week, the Arizona State Transportation Board approved a contract for
Sundt/Kiewit, A Joint Venture, to move forward with construction after six
months of preliminary work.
Ina
Road will close at I-10 on Feb. 15 and is scheduled to remain closed for
a little more than two years. During this time, I-10 will be shifted through
the work zone, and drivers who ordinarily would enter and exit I-10 at Ina Road
should consider using Cortaro or Orange Grove roads.
Access
to businesses will be maintained throughout.
The
project is funded by the Regional Transportation Authority, managed by the Pima
Association of Governments. In addition, the Town of Marana is providing $25
million for work that will widen Ina Road and reconstruct Ina Road bridges over
the Santa Cruz River west of I-10.
ADOT
is managing the project.
Preliminary
construction began last summer with utility work, improvements to frontage
roads and construction of a ramp from Ina Road to the westbound frontage road.
Ina Road has remained open at I-10 but has been restricted to a single lane in
each direction.
In
addition to an Ina Road overpass that will be approximately 25 feet above
ground level, other major improvements include:
·
Widening
I-10 so it can eventually accommodate four lanes of traffic in each direction.
·
Expanding
Ina Road to two lanes in each direction; Ina currently is one lane in each
direction west of I-10 and two lanes in each direction east of I-10.
·
Reconstructing
and updating frontage roads and entrance and exit ramps to meet the new profile
of Ina Road.
·
Landscaping
along the project area that will draw inspiration from the Sonoran Desert.
The
project includes reconstructing the Ina Road bridges over the Santa Cruz River.
This work will close the Pima County Loop Trail, south of Ina Road at Ted
Walker Road and north of Ina Road at the Crossroads at Silverbell District
Park, for approximately two years beginning in mid-January. When the trail reopens,
there will be underpasses on each side of the Santa Cruz River, new access
ramps to Ina Road and new bike lanes and sidewalks along Ina Road.
To see more on this project,
visit azdot.gov/InaTI.
|