PROJECT COMPLETE: 20-21-C1 Riverfront Drive Utilities Extension Project
Contractors for the Water Utilities Department recently completed a project to extend a 12-inch water line along Riverfront Drive (State Hwy 255) from P Street to Spradling Avenue.
Additionally, a sewer pump station and around 600 feet of sewer force main were installed to support an RV Park currently under construction approximately 500 feet north of the Riverfront Drive and P Street Intersection.
Design Consultant: Hawkins-Weir Engineers, Inc. Contractor: Goodwin & Goodwin Inc. Actual Completion Date: 6/3/2023 Total Project Cost: $1,949,835.00
Learn more about City of Fort Smith Water Utilities projects at -fortsmithar.gov/waterutilitiesprojects
|
|
|
|