Westbound lanes of SR 210 in Redlands and Highland will be closed due to the ongoing repaving project by CalTrans, and in Bloomington portions of Interstate 10 will be closed for the bridge demolition project.
Westbound SR 210 to be closed Friday night to Monday morning
![]() |
The second of six 55-hour directional freeway closures of SR 210 is scheduled from 10 p.m. on Friday, April 21 through 5 a.m. on Monday, April 24.
Crews will be performing paving operations on the westbound on-and off-ramps of the San Bernardino Avenue interchange as part of the SR 210 Lane Addition and Base Line Interchange Project.
During this weekend’s closure, motorists transitioning to westbound SR 210 from I-10 will exit at Alabama Street and travel north to access the westbound SR 210 on-ramp at 5th Street/Greenspot Road.
Future directional closures are scheduled for the following dates*:
Westbound Closures:
Eastbound Closures:
About the Project
The SR 210 Lane Addition and Base Line Interchange Project is designed to provide increased traffic flow through this corridor. To eliminate the existing bottleneck and provide lane continuity, the SR 210 will be widened from Sterling Avenue to San Bernardino Avenue in the cities of San Bernardino, Highland, and Redlands, as well as the unincorporated portion of San Bernardino County. Base Line Interchange will also be widened from Buckeye Street to Seine Avenue in the city of Highland, which will include widening three of the four interchange ramps. As the SR 210 Lane Addition and Base Line Interchange projects aligned geographically and shared similar delivery schedules, they were combined for the design, right-of-way, and construction phases to save cost and expedite the schedule. In addition, pavement rehabilitation work was added through a cooperative agreement with Caltrans that includes new concrete pavement between 5th Street and Lugonia Avenue. Adding the pavement rehabilitation work during the Lane Addition and Base Line Interchange projects means one less project that the community will have to navigate around in the future.
For additional information about the project, please visit goSBCTA.com/SR210BaseLine and be sure to follow @goSBCTA on Facebook, Instagram, and Twitter for additional closure updates.
Westbound I-10 to be closed at Cedar Ave for partial bridge demolition
![]() |
![]() |
Crews are also expected to close all westbound lanes of I-10 in Bloomington at Cedar Avenue starting at 8 p.m. on Friday, April 21 through Saturday, April 22 to 4 a.m. Crews will then re-close lanes later on Saturday night on April 22 at 10 p.m., through Sunday, April 23 to 6 a.m. while demolition of the Cedar Avenue bridge continues.
Additionally, Cedar Avenue will be closed between Slover Avenue and Valley Boulevard from 8 p.m. on Friday, April 21 to 4 a.m., Saturday, April 22 and from 10 p.m., Saturday, April 22 to 6 a.m., Sunday, April 23. Drivers will be detoured along Valley Boulevard, Slover Avenue, Riverside Avenue, and Sierra Avenue.
I-10 Cedar Avenue Project construction alerts, project updates and an interactive map detailing lane closures and detours are available on the SBCTA website.
Drivers are encouraged to sign up for weekly text message construction alerts by texting i10Cedar to (888) 525-1021.