3rd Ave S & S Main St Improvements Project Construction Updates

Seattle Department of Transportation logo

3rd Ave S & S Main St Improvements Project Construction Updates

Construction updates: June 20, 2025

Construction on the 3rd Ave S & S Main St Improvements Project is ongoing.  

This weekend (June 21-22) we will not be doing any work. 

Next week, (June 24-27) we will do the following work at the below locations: 

  • 3rd Ave S & S Washington St Intersection, Southeast Lanes
    • Demolish the northwest corner intersection
    • Level the street surface
    • Form and pour concrete panels 

During construction, we will restrict parking and loading on the east side of 3rd Ave. 

Map of the 3rd Ave S and S Main St Bus Stop Improvements project in Pioneer Square, showing the areas where work will occur over the next week.

Map of the 3rd Ave S and S Main St Bus Stop Improvements project in Pioneer Square, showing the areas where work will occur over the next week. Click image for larger image


Thank you for your interest in the 3rd Ave S & S Main St Improvements project and for your patience during construction.

We will host our next virtual Q&A Session on June 24, 2025 from 4-5pm. In this event, we will share project updates and answer the public’s questions regarding our progress and impacts. See the information to join below:  

Join Here  

Meeting ID: 277 814 941 846 

Passcode: AQ7YM3r6 

Contact Us:  

If you have questions, don’t hesitate to reach out via email or phone.     

Matthew Howard  

Communications and Outreach Lead       

3rd Ave S & S Main St. Bus Stop Improvements   