City of Lynnwood Project Update - Scriber Creek Trail Improvement Project - June 13, 2025

Lynnwood Washington

Scriber Creek Trail Improvement - Phase 3


SCT 3 -Preparing for Construction at the 200th ST SW Trail Head

SCT 3 -Preparing for Construction at the 200th ST SW Trail Head


Please follow all pedestrian and traffic control. This portion of the Scriber Creek Trail is fully closed during construction.


May 19 , 2025 - June 13, 2025

  • Crews have completed mobilization of equipment, installation of construction fencing, environmental controls, and construction access points.
  • Crews are working on clearing and grading the trail and bridge sites for major construction to begin next week.
  • Preparation for piledriving of 6"  piles, using a vibratory hammer. Crews will begin driving piles to support bridges next week. 
  • Installation of Fiber Reinforced Polymer (FRP) pedestrian bridges and catwalks. 

Questions during construction? Contact us:

Eric Peterson - Parks Superintendent

email: epeterson@LynnwoodWA.gov

phone: 425-670-5595

Webpage:  Scriber Creek Trail Phase 3


Title VI Non-Discrimination Information


For more information on this project, visit the project website