City of Lynnwood Project Update - Scriber Creek Trail Improvement Project - February 24, 2023

Lynnwood Washington

Scriber Creek Trail Improvement


Crews excavating for signal crossings on the east side of Cedar Valley RD

Crews excavating for signal crossings on the east side of Cedar Valley RD


ROAD CLOSURE

  • January 3, 2023 through Late April, 2023
    • 200th Ave W between Cedar Valley Rd and 52nd Ave W

Please follow all traffic signage for detour routes


Please follow all pedestrian and traffic control.


Weeks of February 20, 2023 And February 27, 2023

Week of February 20, 2023

  • 2/20/23 President’s Day - No Work performed
  • 2/22/23 No work performed due to weather
  • Temporary paving of trench patches
  • Continue placing signal crossings at Cedar Valley RD and 200th St SW intersection
  • Continue clearing in Scriber Creek Park
  • Pile driver’s mobilize to site

Week of February 27, 2023

  • Begin driving piles for Boardwalk #1 on 200th St SW
  • Continue clearing and grubbing in Scriber Creek Park
  • Continue drainage installation at Cedar Valley RD and 200th St SW intersection

Questions during construction? Contact us:

David Meisenheimer - Construction Project Manager

email: davidm@kpg.com

phone: 206-369-3043

Webpage:  www.LynnwoodWA.gov/ScriberCreekTrail


Title VI Non-Discrimination Information


For more information on this project, visit the project website and follow us on Twitter @LynnwoodStreets.