General Updates
-
- Please note that schedules are weather-dependent. Updates will be provided approximately once a week moving forward.
- See Project Phasing Map. (PDF)
-
Amhurst Area
- Weeks of July 6 & 13
- City Forces will be milling and paving the streets.
-
Zachary Lane
- Week of July 6
- Zachary Lane road closure in effect (See Detour Map).
- Continue trail construction.
- Continue vegetation restoration.
- Pave road intersections.
- Relocate private utility handholes and poles.
- Week of July 13
- Continue trail construction.
- Continue vegetation restoration.
- Continue relocation of private utility handholes and poles.
-
Holly Lane
- Week of July 6
- Begin utility spot replacements.
- Begin curb spot removals and replacements.
- Begin trail construction.
- Week of July 13
- Patch pavement.
- Begin vegetation restoration.
For any questions, contact Matt Tang at 763-509-5529 or email mtang@plymouthmn.gov
|
|
|
|