Weekly Construction Update for May 29, 2020

view as a webpage | Bookmark and Share

May 29, 2020

Weekly Construction Update

Village Logo

The following is an update on current and upcoming construction projects within the Village of Milford as of May 29, 2020. Projected dates and timelines are all weather permitting.

Intermittent lane closures may occur as needed, and drivers are asked to drive with caution, and avoid use of cell phones, through work zones as workers will be present. 

 

S. Milford Road Project

Work on the remaining punch list items, including pavement markings and sprinkler repairs, continues.

Peters Road

The Peters Road improvements moved forward this week with the continued installation of the storm sewer and drainage structures. Road grading and aggregate base placement will continue for the next two weeks.

Please note the road will be closed to through traffic for the duration of the project. Residents will still have access but should avoid driving through the current active construction work area if possible.