Zone 2 UPDATE: On August 8, River Road fully reopened while Louisville Water takes a break from pipe work on the road throughout August.
We are still working on Transylvania Avenue near the intersection with Mason Boulevard.
Drivers will notice a smoother ride along River Road. We paved and restriped the road along the route where we completed work. Louisville Water continues to install pipe in other areas.
Work will resume on River Road on Tuesday, September 2. We will start near Glenview Avenue and Lime Kiln Lane. We will repost signage directing drivers to current entry and exit paths around these areas.
 Work in Zone 2 is expected to wrap up in early November. The entire project will continue through this year and into 2026. Our goal is to finish most of the work on River Road by next summer.
Know someone who wants to receive this newsletter? Share this link.
For further information on Councilman Scott Reed or District 16 please visit www.louisvilleky.gov/government/metro-council-district-16
You can also reach out directly by phone at 502.574.1116 or by email at scott.reed@louisvilleky.gov.
601 West Jefferson Street Louisville, KY 40202
Having Trouble Viewing this eNewsletter? Click here to view it on the web.
|