2022 Street Improvements - Project Update 12/2/2022

2022 Street Improvements - Project Update 12/2/2022

Washington Street (Wolf to west end)

Harding Avenue (Wolf to west end)

Columbia Avenue (Wolf to west end)

Paula Lane (Morse to dead end)

Andy Lane (Eisenhower to dead end)

Work on Washington, Harding, Columbia, Paula, and Andy has been substantially completed.  Weather permitting, pavement striping and street sign replacement will take place over the week of December 5. 

Millers Road (400 Block of Millers to dead end)

Millers Road is tentatively scheduled to have the final layer of asphalt pavement paved on Tuesday, December 6.

Howard Avenue (Maple to Des Plaines River Rd)

Howard Avenue is scheduled to have the final layer of asphalt pavement paved on Monday, December 5.  Topsoil and sod placement will occur soon after the paving is completed. 

Wille Road (Marshall to Mt Prospect)

Wille Road is scheduled to have the final layer of asphalt pavement paved on Friday, December 2.  Weather permitting, pavement striping will take place on Monday, December 5.

Prospect Avenue (White to west end)

Prospect Avenue is scheduled to have the final layer of asphalt pavement paved on Monday, December 5.  Topsoil and sod placement will occur soon after the paving is completed.