Water main work on 3rd Ave scheduled to start in late July 2025
Later this month, our crews (with help from Seattle Public Utilities) will begin replacing the 100-year-old water main line on 3rd Ave between Virginia St and Pine St.
Caption: Map of 3rd Ave between Lenora and Pine St. The orange crosshatched area shows 3rd Ave, where we will repave the road. The light blue stippled/dotted areas show where we expect to shut off water.
When will we be doing this work?
-
On weekends we will work from 9 PM on Friday night through 5 AM on Monday morning
-
On weeknights we will work from 7 PM at night until 7 AM in the morning
What about water supply shutoffs?
Our crews will shut off the water supply in the area up to four times on weeknights and weekends. You can expect:
-
Two short shut offs that will last between two to four hours
-
Two longer shut offs that will last between eight to ten hours
-
Seattle Public Utilities will notify you and your neighbors five days before the water is shut off. To maintain water usage for residents and building tenants, a temporary waterline will be installed to provide water throughout the rest of the project timeline. We will reach out when we know more about the exact schedule of the shut offs. SPU will give your business 5-day advanced notice of any shut offs that may impact you.
What else can you expect?
We will also repave parts of 3rd Ave between Virginia St and Pine St while we replace the water main. To do this, we will:
-
Close at least one lane in the road
-
Temporarily close portions of the sidewalk on either side of the street
-
Temporarily close a crosswalk
-
Block access to some entrances or driveways
-
Temporarily close and move bus stops
You should also expect noise, dust, vibrations, and construction equipment around the work area while we work
Before we begin, we will share detour routes. We will continue to update our webpage and send emails with more information about the project schedule, construction activities, and what to expect during construction.
Upcoming Work Schedule
July 28-August 3
Between Stewart St and Virginia St
-
We will:
- Shift traffic from the west side of 3rd Ave to the east side between Stewart St and Virginia St
- Both lanes will remain open in either direction, though they will be slightly narrower as we are working within the parking lane
-
Cut open the concrete panels on the street
-
Demolish those concrete panels, exposing the water main
-
Install a temporary water main to maintain water service throughout the project
Paving Work:
3rd Ave, between Stewart & Virginia, East Curb Lane to the Center of the street
-
We will:
- Measure the street’s elevation and shape
3rd Ave, between Pine to Stewart, West Curb Lane to the Center
-
We will:
- Cut two concrete panels with a saw, which will help us remove them
-
Demolish those concrete panels
-
Ensure the street surface is level and even
-
Pour two new concrete panels
For questions or concerns, contact Matthew Howard, Outreach Lead, at 3rdAveImprovements@seattle.gov or (206) 900-8729.
|