Stay Informed! Denny Way Paving Project Update

Seattle Department of Transportation logo

Stay Informed! Denny Way Paving Project Update

Nighttime paving on Denny Way coming up June 4 and June 5

Image showing construction workers installing new sidewalk for the Denny Way Paving Project

Our construction work on the Denny Way Paving Project continues. We're paving almost 12 blocks of Denny Way to make using Denny Way easier and better for residents and commuters alike. Our work includes asphalt paving, sidewalk upgrades, bus stop changes, new pedestrian ramps, areas of widened sidewalks that shorten crossing distances, new stop bars painted on the street, and new "no turn on red" signs. 

Here’s what you'll find in this email update: 

  • What We're Doing Next Week 
  • What You Need to Know About Upcoming Lane Closures
  • Nighttime Paving Work on Denny Way - June 4 and June 5
  • How You Can Stay Up to Date on the Project   

What We’re Doing Next Week

Construction will continue next week on Denny Way between 5th Ave and Boren Ave. Our work will reduce the number of lanes on Denny Way and close some parts of the sidewalk. If you are travelling in the area, watch for changing traffic patterns, and follow any signs that direct you around work zones.

We know this will make using Denny more of a challenge. Thank you for your patience while we work. When we’re done working, you will be able to cross the street more easily because of the newly extended curbs and pedestrian ramps. You'll also have an easier time getting to the bus or nearby businesses. 

Map detailing upcoming lane closures and sidewalk work on Denny Way

Map showing work areas on Denny Way.

What You Need to Know About Lane Closures on Denny Way:

Between Dexter Ave to 9th Ave – Westbound Lane Closure

  • May 23: One westbound lane of Denny Way closed from 9 AM to 3 PM for sidewalk work. 

Between Westlake Ave to Terry Ave – Westbound Lane Closure

  • May 27 to May 30: One westbound lane of Denny Way and one northbound lane of Westlake Ave closed from 9 AM to 3 PM for sidewalk work. 

Between 9th Ave to Westlake Ave – Eastbound Lane Closures

  • May 23: One eastbound lane of Denny Way and one southbound lane of Westlake Ave closed from 9 AM to 3 PM for sidewalk work. 

Between Terry Ave to Boren Ave – Eastbound Lane Closures

  • May 29 to May 30: One eastbound lane of Denny Way closed from 9 AM to 3 PM for sidewalk work.

Between 5th Ave to Westlake Ave – Westbound and Eastbound Lane Closures

  • May 23: Two westbound lanes of Denny Way closed from 9 AM to 3 PM for two blocks at a time as crews install systems that detect vehicles and assist with traffic signal operations.
  • May 27 to May 30: Two eastbound lanes of Denny Way closed from 9 AM to 3 PM for two blocks at a time as crews install systems that detect vehicles and assist with traffic signal operations
Images showing overnight paving work

Nighttime Paving Work on Denny Way - June 4 and June 5

We are laying the new asphalt surface on Denny Way on June 4 and 5. This work will bring us to the halfway point in the project. We will be doing this work overnight to reduce traffic impacts during the day. We will always keep one lane open in each direction on Denny Way, but two lanes will be closed so that we can lay the new road surface. We will also close several intersections.

Between 5th Ave and Westlake Ave – Eastbound and Westbound Lane Closures  

  • Night of June 4: Two eastbound lanes on Denny Way will be closed from 7 PM to 5 AM for paving work. Northbound intersections at Taylor Ave, Vine St, 6th Ave, Dexter Ave, 8th Ave, Bell St and 9th Ave will be closed during the same time frame with traffic detours posted.
    Night of June 5: Two westbound lanes on Denny Way will be closed from 7 PM to 5 AM for paving work. Southbound intersections at Taylor Ave N, 6th Ave N, Dexter Ave N and 9th Ave N will be closed during the same time frame with traffic detours posted.
Construction sign reading "Road Work Ahead" with sidewalk detour signs in the background

How You Can Stay Up to Date on the Project 

Thank you for your support during construction, and please don’t hesitate to reach out with any questions or comments.  

Sincerely, 

Darrell Bulmer

Denny Way Paving Project Communications and Outreach Lead

Seattle Department of Transportation

Để biết thông ,n bằng ngôn ngữ của quý vị về việc chúng tôi thay thế bề mặt đường và thực hiện các cải ,ến khác trên đường Denny Way, vui lòng gọi (206) 257-2243. Vui lòng cho chúng tôi biết bằng ,ếng Anh ngôn ngữ mà quý vị muốn sử dụng. Chúng tôi cung cấp miễn phí dịch vụ phiên dịch và thông dịch. 

有關我們在 Denny Way 上重鋪路面和進行其他安全改進工程的資訊(以您的語言),請致電 (206) 257-2243。請用英語 告訴我們您想要的語言。我們免費提供筆譯和口譯服務。

Si desea información en su idioma acerca de nuestro trabajo de reemplazo de la superficie de la carretera y otras mejoras en Denny Way, llame al (206) 257-2243. Díganos en inglés cuál es su idioma preferido. Ofrecemos servicios de traducción e interpretación gratuitos.

Learn More