Trenching work at the southwest corner of 8th Ave N and Westlake Ave. Steel plates are set over the trench to help traffic continue onto 8th Ave N. Please use caution when traveling through this area.
Dear Community Members,
Construction continues along Westlake Ave as part of the Route 40 Transit-Plus Multimodal Corridor Project. These upgrades will improve transit reliability, pedestrian access, and street safety.
To learn more about the Fremont and Westlake construction activities, visit our project webpage or check out our recent SDOT blog post.
What's Happening in Westlake?
This week, we have six key construction updates to share:
-
Preparing for final restoration at N Halladay St and Westlake Ave Crews are currently coordinating to install a temporary connection for street lighting on Westlake. Once this is complete, most likely in late February or early March, conduit work will be finished, and installation of sidewalks will commence. This work includes curb ramps on both sides of Westlake and the parking lot on the east side of the street for the new crosswalk. The trenches crossing Westlake and the parking lot are currently backfilled and patched paved. Once the weather warms up, crews will return to complete the final paving restoration at these locations. Folks can expect lane restrictions and some minor delays through the area.
-
Preparing for final restoration at Crockett St
Crews are wrapping up the updates at Crockett St. Crewmembers will lay down new striping to complete the final step of this construction later this year when warmer weather arrives so striping will adhere to the new roadway properly.
-
Sidewalk upgrades near 8th Ave N and N Galer St
Crews will demolish and upgrade sidewalks near 8th Ave N and N Galer St on Westlake Ave. Expect detours for pedestrians and wheelchair users, as well as temporary lane restrictions. Crews will work on select corners at a time to maintain crosswalk access. This work is tentatively scheduled to take around two weeks but winter weather is always capable of shifting the schedule.
-
New pedestrian curb ramps are being installed near the Westlake Cycle Track. This will allow rollers and cyclists easy approaches and access to this important path.
-
Preparing for construction at Aloha St./9th Ave
Crews are expected to mobilize into this location in the last week of February or early March. The work consists of trenching for fiber optic conduits from the intersection running north along the west side of the parking lot on the east side of Westlake. The purpose of this installation is to connect traffic signals along Westlake, allowing them to “talk” to each other and keep traffic moving more efficiently.
-
Pedestrian signal upgrades and street improvements are moving forward, with work on sidewalks and crossings ongoing. We appreciate the Westlake neighborhood’s patience
Route 40 has over 8,500 average weekday daily boardings (Fall 2024) - an 11% increase from Fall 2023. It is the fifth (5th) highest ridership route in the Metro network.
In addition to the 5-10% transit travel time savings, 14-17% in Ballard to Downtown, the Route 40 project will maintain and modernize vital infrastructure
- Temporary lane reductions
- Temporary driveway closures
- Temporary bus stop closures
- Temporary parking restrictions
- Temporary sidewalk detours
- Temporary storage of construction supplies in the street
- Temporary noise, dust and vibrations
- Bus stop relocations
- Drainage work: This involves digging trenches to help manage water flow
- Signal pole foundation excavation: This work involves digging for the pole foundations prior to when we order custom signal poles which takes a while to build and to make sure we know there are no underground obstructions
- Trenching for conduit: This involves digging trenches to lay down pipes or cables underground
- Sidewalk curb bulb out: This involves making the curbs stick outward for safety or accessibility
- Mill and fill overlay: This is when the top layer of the road gets removed and replaced with new asphalt
The construction timeline is always subject to change depending on weather conditions and materials availability. We are committed to keeping you informed and maintaining open communication throughout the remainder of this project.To learn more about the project and designs, visit our online open house.
If you own or manage a business in Fremont or Westlake Ave near the project corridor and would like to be featured, please email us at Route40@seattle.gov and send us a short description and picture of your business.
-
Phone: (206) 775-8731 (leave a voicemail and we will return your call)
Our project team is in close coordination with the following projects. Please visit their project webpage to see the latest update:
If you need this information translated, please call 206-775-8731.
如果您需要此信息翻譯成中文 請致電 206-775-8731.
Kung kailangan mo ang impormasyon na ito na nakasalin sa Tagalog mangyari lamang na tumawag sa 206-775-8731.
Si necesita traducir esta información al español, llame al 206-775-8731.
Odeeffannoon kun akka siif 206-775-8731.
Nếu quý vị cần thông tin này chuyển ngữ sang tiếng Việt xin gọi 206-775-8731.
የዚህን መረጃ ትርጉም ከፈለጉ፣ በዚህ ስልክ ቁጥር ይደውሉ፡ 206-775-8731.
ናይዚ ሓበሬታ ትርጉም እንተደሊኹም፣ በዚ ቁጽሪ ስልኪ ይድውሉ፡ 206-775-8731.
당신이 번역이 정보를 필요로하는 경우에, 206-775-8731 로 전화 해주십시오.
اذا تريد ترجمة هذه المعلومات, يرجى الاتصال برقم 206-775-8731
|