Two crewmembers perform trenching work for the new bus stop off Westlake Ave and Halladay St with the help of an excavator.
Dear Community Members,
Construction is underway along Westlake Ave for the Route 40 Transit-Plus Multimodal Corridor Project.
To learn more about what to expect during construction, please visit the project webpage which provides detailed information on construction activities and construction locations in Fremont and along Westlake Ave. You can also read our SDOT blog post.
What's happening in Westlake?
Crews continue trenching across the parking lot south of Halladay St to install conduit. In addition, crews continue demo work and the installation of a new pedestrian curb ramp near the Westlake Cycle Track. We're also continuing to work on a new pedestrian signal, street improvements, and upgraded sidewalks.
Street upgrades on Crockett St and Westlake Ave has started. Please expect to see some driving lanes closed and bus stops temporarily moved. Sign up for transit alerts to get up to date information.
Work on 8th Ave N and Galer St is starting as soon as early February. Neighbors can expect to see temporary street and sidewalk closures during construction.
Community Impacts:
- Noise, dust, and increased vehicle traffic.
- Temporary parking restrictions, driveway closures, and traffic adjustments.
- Night and weekend work to reduce daytime disruption.
- Potential short-term utility service impacts.
- Please use caution driving over metal plates.
Route 40 has over 8,500 average weekday daily boardings (Fall 2024) - an 11% increase from Fall 2023. It is the fifth (5th) highest ridership route in the Metro network.
In addition to the 5-10% transit travel time savings, 14-17% in Ballard to Downtown, the Route 40 project will maintain and modernize vital infrastructure
- Temporary lane reductions
- Temporary driveway closures
- Temporary bus stop closures
- Temporary parking restrictions
- Temporary sidewalk detours
- Temporary storage of construction supplies in the street
- Temporary noise, dust and vibrations
- Bus stop relocations
- Drainage work: This involves digging trenches to help manage water flow
- Signal pole foundation excavation: This work involves digging for the pole foundations prior to when we order custom signal poles which takes a while to build and to make sure we know there are no underground obstructions
- Trenching for conduit: This involves digging trenches to lay down pipes or cables underground
- Sidewalk curb bulb out: This involves making the curbs stick outward for safety or accessibility
- Mill and fill overlay: This is when the top layer of the road gets removed and replaced with new asphalt
The construction timeline is always subject to change depending on weather conditions and materials availability. We are committed to keeping you informed and maintaining open communication throughout the remainder of this project.To learn more about the project and designs, visit our online open house.
Take a walk around multiple Fremont restaurants while enjoying soup, collecting Souper Stickers in your Soupassport, and winning Super Souper Swag. Support your soup community! Pull on your rain boots and coats, brave the dark, cozy up to the best Soups in the Center of the Universe. Learn more about this event by clicking here.
If you own or manage a business in Fremont or Westlake Ave near the project corridor and would like to be featured, please email us at Route40@seattle.gov and send us a short description and picture of your business.
-
Phone: (206) 775-8731 (leave a voicemail and we will return your call)
Our project team is in close coordination with the following projects. Please visit their project webpage to see the latest update:
If you need this information translated, please call 206-775-8731.
如果您需要此信息翻譯成中文 請致電 206-775-8731.
Kung kailangan mo ang impormasyon na ito na nakasalin sa Tagalog mangyari lamang na tumawag sa 206-775-8731.
Si necesita traducir esta información al español, llame al 206-775-8731.
Odeeffannoon kun akka siif 206-775-8731.
Nếu quý vị cần thông tin này chuyển ngữ sang tiếng Việt xin gọi 206-775-8731.
የዚህን መረጃ ትርጉም ከፈለጉ፣ በዚህ ስልክ ቁጥር ይደውሉ፡ 206-775-8731.
ናይዚ ሓበሬታ ትርጉም እንተደሊኹም፣ በዚ ቁጽሪ ስልኪ ይድውሉ፡ 206-775-8731.
당신이 번역이 정보를 필요로하는 경우에, 206-775-8731 로 전화 해주십시오.
اذا تريد ترجمة هذه المعلومات, يرجى الاتصال برقم 206-775-8731
|