Rainier Ave S Bus Lane Project Update - January 10

Seattle Department of Transportation logo

Thank you for your interest in the Rainier Ave S Bus Lane Project to make transit an accessible, convenient, and reliable transportation choice for everyone living in, working in, and visiting the Rainier Valley. Please feel free to share this information with your fellow neighbors and encourage them to sign up to receive updates using this link.

Rainier Ave S Bus Lane Project Update

Construction of the Rainier Ave S Bus Lane Project began on September 3! Crews will work in segments along the project area through spring 2025.

Continue visiting our project website or subscribe to our email list for bi-weekly updates on construction activities.


Over the next two weeks, you'll see the following construction activities along Rainier Ave S:

Rainier Ave S and S Grand St

  • On Friday, January 10 and Monday, January 13, crews will pour and patch concrete on both northbound and southbound shoulder lanes at Rainier Ave S and S Grand St northbound

    • This work will require temporary lane shifts and this part of Rainier Ave S will maintain one lane in each direction

  • Monday, January 13 through Thursday, January 16, crews will be preparing, pouring, and temporary patching the center lanes of Rainier Ave S at the intersection of Rainier Ave S and S Grand St

Rainier Ave S sidewalk repair

  • Tuesday, January 14 through Friday, January 24, crews will be demolishing, preparing, and pouring concrete on the sidewalk of Rainier Ave S between:

    • S Forest St and MLK Jr Way S

    • S College St and 25th Ave S

    • S Hill St and S Walker St

      • The northbound bus stop 8440 on Ranier Ave S, between S Hill St and S Walker St, will be temporarily closed from January 16th through January 24th

    • S Plum St and 23rd Ave S 

Work schedule: 

  • Crews will not be working on Monday, January 20, in observance of Martin Luther King Jr Day 

What to expect during construction

Typical work hours are Monday - Friday, from 7:00 AM to 4:00 PM. During this time you can expect:

  • Temporary traffic revisions to accommodate construction vehicles and equipment
  • Temporary parking restrictions near work zones
  • Noisy construction activities, such as vehicle backup alarms for safety, heavy truck use, and the use of power tools.

Construction Progress

Crews installing electrical vaults before pouring concrete on new sidewalk on east side of Rainier Ave S and S Grand St.

Crews installing electrical vaults before pouring concrete on new sidewalk on east side of Rainier Ave S and S Grand St.

Crews backfilling the east side of Rainier Ave S and S Grand St.

Crews backfilling the east side of Rainier Ave S at S Grand St.

Project Background

Project map showing extension of northbound bus only lane on Rainier Ave S.

Project map showing extension of northbound bus only lane on Rainier Ave S, sidewalk repair work, and safety improvements at Rainier Ave S/S Grand St and Rainier Ave S/S College St.


This project includes the extension of the northbound bus lane on Rainier Ave S from S Walden St to S State St, along with other safety changes requested by community members to make it easier and safer to get around on this busy street. This project will improve the reliability of the Route 7 bus and get us ready for the future RapidRide R Line.

Through collaboration with King County Metro, our goal is to make transit an accessible, convenient, and reliable transportation choice. This project includes:

  • New red painted bus lane between S Walden St and S State St in the northbound direction
  • Sidewalk repair in areas where the most people walk and take the bus on Rainier Ave S
  • At S College St and S State St:
    • New signals to make it easier and safer for people to cross the street
    • New marked crosswalks
    • ADA-compliant curb ramps
    • New Streetlights

We've been reaching out to community members, community-based organizations, and businesses in the project area and will continue to do so in the next few weeks. We want to share construction information with neighbors and community members.

Please visit our website to learn more about the project, and sign up to receive project updates. You can email us at TransitLanes@seattle.gov or call at (206) 257-2201.


Sincerely,

Ching Chan
Public Engagement Lead
City of Seattle, Department of Transportation

How to stay informed


Blue Bullhorn Icon

Sign up for the SDOT Newsletter

Stay up to date on Seattle's transportation news. You'll receive our top highlights delivered straight to your inbox each month. – Subscribe here