November 14, 2024
The bridge will be open this weekend, November 15 through November 18. The next bridge closure is scheduled for Friday, November 22 through Monday, November 25. We will send an email one or two days ahead of the scheduled closure to confirm or cancel it. Thank you for your patience as we work to complete tasks as efficiently as possible while navigating changing weather forecasts.
Work continues north of the Ballard Bridge on 15th Ave NW between NW Market St and NW Leary Way. As always, Ballard businesses are open during construction. Please support them by shopping locally!

Crews continue to work along 15th Ave NW at NW Market St, NW 52nd St, NW 51st St, NW 50th St, NW 49th St, and Leary Way NW. Through this construction we will upgrade ADA accessible ramps, rebuild sidewalk corners, install upgraded traffic signals and cameras, improve storm drainage, and repair the sidewalk and roadway in select areas.
At NW 51st St, crews continue electrical and signal lighting work for the new pedestrian and bicycle crossing. Crews also continue electrical work at Leary Way NW and they will soon begin work to strengthen and improve earthquake safety on the Leary Way Bridge.
-
Construction is typically scheduled Mondays – Fridays from 7 AM – 5 PM.
-
We will close driving lanes on 15th Ave NW near work areas and on Leary Way NW beneath and near the bridge. There will always be at least one lane open in each direction.
-
We will close the sidewalk in work areas. There will be detour signs in place to direct you around construction.
-
We will close streets to thru traffic as needed between 17th Ave NW and 14th Ave NW. You will still be able to walk, roll, bike, or drive to businesses and homes on these streets.
- We will temporarily move bus stops for the D Line at 15th Ave NW and NW Market St. Bus stops for the D Line, Route 17, and Route 40 at 15th Ave NW and Leary Way NW may also be temporarily moved. Please see signs at bus stops for new locations and/or sign up for transit alerts.
-
We will temporarily change parking in some areas for construction staging and traffic control near work sites.
 Please remember that Ballard Bridge closure dates may change based on weather conditions. We will send an email one or two days ahead of the scheduled closure to confirm or cancel it.
 Crews dig a trench across Leary Way NW on the east side of 15th Ave NW for an underground electrical conduit to upgrade traffic signals.
   Crews break up old concrete in preparation for new sidewalks on the east side of 15th Ave NW between NW 52nd St and NW 51st St.
-
Phone: (206) 512-3950 (leave a voicemail and we will return your call)
The 15th Ave W/NW and Ballard Bridge Paving and Safety Project is funded by the
The City of Seattle is paving 15th Ave W/NW from W Emerson St to NW 57th St. To request translation of these materials, call (206) 512-3950.