Thank you for your patience as we continue construction on the 15th Ave W/NW corridor and Ballard Bridge.
Below we have outlined the work we will do over the next few weeks and what to expect in terms of travel, noise, and other impacts. Anticipated work locations may change as crews demolish, install, and complete improvements as efficiently as possible.
Businesses remain open during construction. Please support Ballard businesses by shopping locally!
 
Starting as early as Monday, August 12, crews will begin overnight work at the 15th Ave NW and NW Market St intersection. This work will be overnight Monday – Friday from 7 PM – 5 AM to minimize traffic impacts. Neighbors should expect nighttime work to last at least one week. This work will involve digging trenches for cables in preparation for upgraded traffic signals and traffic cameras at the 15th Ave NW and NW Market St intersection.
-
As part of our nighttime work at the 15th Ave NW and NW Market St intersection, we will temporarily reduce driving lanes in each direction. Turn lanes in each direction will still be available. A uniformed police officer may be present to help direct traffic. Detour signs will be in place to direct people walking around construction.
Crews continue to work on the west side of 15th Ave NW between NW 58th St and NW Market St. Crews will also soon begin demolition at the corners of the 15th Ave NW and NW Market St intersection. This construction is scheduled Mondays – Fridays from 7 AM – 5 PM. Through this work, crews will upgrade the ADA accessible ramps, rebuild sidewalk corners, and repair the sidewalk and roadway in select areas.
-
There will be two driving lanes of 15th Ave NW open in each direction except from 9 AM – 2 PM when there may be only one lane open in each direction. We will close the sidewalk in the areas where we're working on 15th Ave NW between NW 58th St and NW 54th St. There will be detour signs in place to direct you around construction.
-
We will close NW 57th St and NW 56th St to thru traffic as needed between 17th Ave NW and 14th Ave NW. You will still be able to walk, roll, bike, or drive to businesses and homes on these streets.
-
We will temporarily move the D Line bus stops at 15th Ave NW and NW Market St. Please see bus stops for new locations and/ or sign up for transit alerts.
-
We will temporarily change parking in some areas for construction staging and traffic control near work sites.
Partial bridge closures are scheduled Monday evenings - Friday mornings 7 PM - 8 AM. Overnight closures of Ballard Bridge for pavement restoration will continue through the week of August 12.
Crews will complete preliminary paving, maintenance, and preservation work to keep the 107-year-old bridge safe and strong. The remaining bridge work will be completed during the full bridge closures scheduled over several weekends this fall.
As a reminder, detour routes will be in place for people who drive or use transit. We’ll do our best to keep the bridge open for people walking, rolling, and biking unless it’s unsafe. We’ll share more details about detour routes and how to get around during full bridge closures in a future update.
For our overnight bridge work, we need to temporarily close some lanes of traffic, move a couple of bus stops, and close one side of the walking, rolling, and biking path.
-
8 AM – 7 PM The bridge will operate normally, with two lanes open in both directions.
-
7 PM - 10 PM: We will close two driving lanes on the bridge, leaving one lane open in each direction.
-
10 PM - 5 AM: We will close the bridge to southbound traffic, leaving one lane open in the northbound direction. If you are driving southbound at this time, please take the Aurora Bridge.
-
5 AM – 6 AM: We will close two driving lanes on the bridge, leaving one lane open in each direction.
-
6 AM – 8 AM: We will close one driving lane on the bridge, leaving two southbound lanes open and one northbound lane open.
 If you are riding south on the D Line bus...
-
10 PM - 5 AM: The bus stop at 15th Ave NW and Leary Way NW will be moved to the Route 40 bus stop on the south side of Leary Way NW where it intersects with 15th Ave NW. On the south end of the bridge, the D Line bus stop at 15th Ave W and W Emerson St will be moved south on 15th Ave NW. It will be right across from W Ruffner St.
-
There are no changes to the D Line bus stops if you are riding north and all bus routes and stops return to normal outside of the 10 PM - 5 AM window.
-
We encourage you to follow King County Metro’s service advisories and sign up for transit alerts to stay informed.
If you are walking, rolling, or biking...
-
7 PM - 6 AM: We will close the path on the east side of the bridge for people who walk, roll, or bike. If you are traveling across the bridge at this time, please use the path on the west side.
-
If you are traveling south, please cross at Leary Way NW.
-
If you are walking north, please use the stairs on the east side of 15th Ave W to cross under the bridge and get to the path on the west side. See map below.
-
For anyone rolling or biking north, you can detour by taking the RapidRide D Line bus north from bus stop #14190 at 15th Ave W and W Emerson St.

 A businesses are open sign set alongside the newly installed sidewalk pavement on 15th Ave NW.
 A section of concrete that has been removed from a lane of 15th Ave NW.
-
Phone: (206) 512-3950 (leave a voicemail and we will return your call)
The 15th Ave W/NW and Ballard Bridge Paving and Safety Project is funded by the
The City of Seattle is paving 15th Ave W/NW from W Emerson St to NW 57th St. To request translation of these materials, call (206) 512-3950.