What's Happening Now?
Our contractor is wrapping up trenching work across NW Market Street and Ballard Ave. The crews will be hard at work in August to continue installation on the conduit and to perform curb ramp and sidewalk improvement work.
Construction on Leary Ave NW, between NW Dock Pl and NW Ione Pl, will also be starting. Continue reading below for more information.
 Crew members perform trenching work on NW Market St and Ballard Ave NW for new pipes and cables with the help of an excavator.
What’s happening in Ballard?
-
NW Market St between Ballard Ave NW and 22nd Ave NW (both sides of the street):
-
- Stormwater drainage improvements and electrical trenching for improved crossings. Some of this work will require some sidewalk demo so please make sure to use all pedestrian detours.
- Curb ramp improvements. The crews are scheduled to continue work on the crossing near NW Market St through early August. Pedestrians will have maintain access but may need to take slight detours.
- Sidewalk and bus zone improvements: Crews will work on select sidewalk repairs and update the bus zones on both north and south sides of NW Market St. Please see bus design changes here.
- Neighbors should expect to see lane reductions on NW Market St through August during non-peak hours (9 AM-3 PM), on weekdays and weekends. Parking restrictions along NW Market St is also expected for staging and construction activity. Please sign up for rider alerts if your transit stop is in this area.
- We are expecting that access to stores and businesses will still be available during their open hours. Please continue to shop and support Ballard businesses.
-
Leary Ave NW
- Between 20th Ave NW and NW Market St:
- Crews will continue trenching to update the drainage and installing electrical conduit for future pedestrian crossing improvements. This involves digging trenches to lay down pipes or cables underground. Neighbors should expect to see work on this intersection off and on through the Summer and Fall.
- Between NW Dock Pl and NW Ione Pl:
- Crews will begin their work on sidewalk, curbramp, and bus zone improvements as soon as August 5. Community members can expect new paving and larger bus bulbs in both directions of Leary Ave NW. This will require sidewalk demolition, electrical trenching, and curb work. Pedestrians will be directed to use detours down to Ballard Ave NW.
- To learn more about the planned improvements on Leary Ave NW, you can click here.
- Neighbors should expect to see temporary lane reductions, sidewalk detours, and parking restrictions in select areas of Leary Ave NW throughout the Summer and Fall. Construction is typically weekdays and select weekends from 7 AM - 4 PM.
What’s happening in North Aurora?
Crews continue to upgrade the bus zone on Aurora Ave N and N 105th St/N Northgate Way. Neighbors and travelers should expect lane reductions during weekdays from 9 AM - 3 PM heading eastbound on N 105th St/N Northgate Way, just east of Aurora Ave N. These lane reductions are expected to extend through most of August.
What’s happening in Fremont and Westlake?
While civil work—like Watermain Utilities, pavement upgrades, and sidewalks—in Fremont won’t begin until early 2025, community members may continue to see crews doing some short-term prep work before major construction occurs. Please note, there may be temporary traffic impacts.
Westlake Ave N construction could begin as early as Fall 2024.
- Temporary lane reductions
- Temporary driveway closures
- Temporary bus stop closures
- Temporary parking restrictions
- Temporary sidewalk detours
- Temporary storage of construction supplies in the street
- Temporary noise, dust and vibrations
- Bus stop relocations
- Drainage work: This involves digging trenches to help manage water flow
- Signal pole foundation excavation: This work involves digging for the pole foundations prior to when we order custom signal poles which takes a while to build and to make sure we know there are no underground obstructions
- Trenching for conduit: This involves digging trenches to lay down pipes or cables underground
- Sidewalk curb bulb out: This involves making the curbs stick outward for safety or accessibility
- Mill and fill overlay: This is when the top layer of the road gets removed and replaced with new asphalt
The construction timeline is always subject to change depending on weather conditions and materials availability. We are committed to keeping you informed and maintaining open communication throughout the remainder of this project.To learn more about the project and designs, visit our online open house.
-
Phone: (206) 775-8731 (leave a voicemail and we will return your call)
Our project team is in close coordination with the following projects. Please visit their project webpage to see the latest update:
If you need this information translated, please call 206-775-8731.
如果您需要此信息翻譯成中文 請致電 206-775-8731.
Kung kailangan mo ang impormasyon na ito na nakasalin sa Tagalog mangyari lamang na tumawag sa 206-775-8731.
Si necesita traducir esta información al español, llame al 206-775-8731.
Odeeffannoon kun akka siif 206-775-8731.
Nếu quý vị cần thông tin này chuyển ngữ sang tiếng Việt xin gọi 206-775-8731.
የዚህን መረጃ ትርጉም ከፈለጉ፣ በዚህ ስልክ ቁጥር ይደውሉ፡ 206-775-8731.
ናይዚ ሓበሬታ ትርጉም እንተደሊኹም፣ በዚ ቁጽሪ ስልኪ ይድውሉ፡ 206-775-8731.
당신이 번역이 정보를 필요로하는 경우에, 206-775-8731 로 전화 해주십시오.
اذا تريد ترجمة هذه المعلومات, يرجى الاتصال برقم 206-775-8731
|