Ship Canal Water Quality Project update 10/13/22

Seattle Public Utilities and King County logos - white
Ship Canal Logo

Have you spotted the recent additions to the neighborhood?

Temporary art installations are displayed at four Ship Canal Water Quality Project sites.

Temporary art installations are displayed at four Ship Canal Water Quality Project sites

We recently installed four new temporary art pieces in Ballard, East Ballard, Fremont, and Wallingford. Enjoy the start of fall with a stroll through the Ship Canal project corridor to look for these pieces and learn about their stories. You can learn more about the artists and their art on our website.

FLOW: Art Along the Ship Canal is a program that uses our construction fences as a backdrop to allow artists to showcase their unique voice and perspective. Many of our public art pieces focus on sustainability and the love of water. This edition of FLOW art features vibrant tapestries, kaleidoscopes, a visual love letter, and the celebration of immigrants.

To learn more about the project, visit our project website. We also continue to update our Flickr albums with recent construction photos.


MudHoney graphic

MudHoney

MudHoney, our 18-ft diameter tunnel boring machine, has currently tunneled over 6,000 feet! Follow along with our tunneling tracker on our project website.

Ground monitoring is ongoing along the tunnel alignment and is done from both inside MudHoney and on the surface.


Ballard

Our Ballard shaft site near Shilshole Ave NW will continue to be busy with tunneling activities until MudHoney reaches Wallingford in 2023.

During regular tunneling activities, you should anticipate:

  • Truck deliveries of concrete segments and MudHoney equipment
  • Nighttime segment deliveries and tunnel spoils being hauled off
  • Noise and vibrations typical of a construction site

Crews are working 24 hours a day, six days a week. Sunday work may also occur. The Ballard shaft site is also the site of the future pump station.

Puget Sound Energy (PSE) has started utility relocation work between 28th Ave NW and NW 56th St. After work on this intersection is complete, they will begin work between 26th Ave NW and NW 56th St.

Neighbors should have received notification directly from PSE. Please contact their project manager, Eric Liaw at eric.liaw@pse.com if you have any questions.


East Ballard

Crews continue building the mechanical and electrical vault on NW 45th St and the diversion structure on 11th Ave NW.

Local closures and detours:

  • One-lane closure on 11th Ave NW through November 2022. Traffic signals direct northbound and southbound traffic on 11th Ave NW and eastbound traffic on NW 45th St as well as bicyclists and pedestrian trail users. During working hours, flaggers will assist with construction vehicles entering and exiting the site. Directional signage is also in place. For safety, bicyclists should either dismount or cross train tracks at a 90-degree angle. Please use extra caution in wet weather as ramps may be slippery.
  • NW 45th St remains closed to traffic between 11th Ave NW and 9th Ave NW; vehicles must detour onto NW 46th St
  • Burke-Gilman Trail detour to the north side of NW 45th St through the project area

You should anticipate:

  • Heavy equipment in the area
  • Noise and vibrations typical of a construction site

Regular work hours will be Monday through Friday, from 7 am to 5 pm. Night and weekend work may occur.


Fremont

Crews continue working on the diversion structure on 2nd Ave NW, including building forms for the structure’s concrete walls. Preparations continue as we plan to resume tunneling our 8-ft diameter tunnel beneath the Ship Canal in early November.

Local closures and detours:

  • 2nd Ave NW, between Leary Way NW and NW Canal St, is closed to vehicle and pedestrian traffic through the end of 2022. NW Canal St is open to two-way traffic to allow access during this closure.
  • NW 36th St, between Leary Way NW and 3rd Ave NW, is closed through late 2023
  • Pedestrian detours on Leary Way NW; please follow all detour guidance on site

You should anticipate:

  • Truck traffic on Leary Way NW as trucks bring materials and equipment to and from the site
  • Generators and fans running during work hours to power pumps and equipment, and to provide fresh air to crews
  • Crane on-site to lower pipe segments for tunneling
  • Noise and vibrations typical of a construction site

Regular work hours will be Monday through Friday, from 7 am to 5 pm. Crews also continue to work on large eight-foot conveyance tunnel pipes underneath white tents within the site from 7 am to 10 pm on weekdays, and possibly 9 am to 10 pm on weekends, over the next few weeks.


Wallingford

Crews completed constructing the walls of the underground odor control facility, which will be housed on the east side of the shaft. Later this month crews will begin removing the remaining contaminated soils in the southwest corner of the site.

You should anticipate:

  • Concrete trucks coming in and out of the site
  • Noise and vibrations typical of a construction site

Regular work hours will be Monday through Friday, from 7 am to 5:30 pm.


Queen Anne

Crews continue preparing to install a large conveyance pipe between the diversion structure and the shaft.

Local closures and detours:

  • Localized Ship Canal Trail detour at least through summer 2023 (see map). Please continue to remain alert when moving through this area.
  • West Ewing Mini Park parking closure through mid-2023

You should anticipate:

  • Trucks coming in and out of the site
  • Noise and vibrations typical of a construction site

Regular work hours will be Monday through Friday, from 7 am to 5 pm. Night and weekend work may occur.


Contact us

Please email SPU_ShipCanalProject@seattle.gov with questions or comments or call our hotline at (206) 701-0233. You can also find information online at spushipcanal.participate.online. To support the community during active tunneling, we have changed our hotline hours to 24 hours a day, Monday through Friday.


Construction Safety is Everyone’s Job

Check out some top safety tips at www.seattle.gov/utilities/constructionsafety


AlertSeattle 

AlertSeattle is the official emergency notification system used by the City of Seattle to communicate with city residents during emergencies. Sign up to receive free alerts from the City via text message, email, voice message, or social media.

Sign-up for AlertSeattle

Update your existing AlertSeattle preferences

Alert Seattle Logo

Visit Project Website