Ballard & MudHoney
MudHoney, our 18-ft diameter tunnel boring machine, recently resumed regular tunneling operations after grinding through a 10-ft boulder.
During regular tunneling activities, you should anticipate:
- Truck deliveries of concrete segments and MudHoney equipment
- Nighttime segment deliveries and tunnel spoils being hauled off
- Noise and vibrations typical of a construction site
Crews are working 24 hours a day, six days a week and will continue until MudHoney reaches Wallingford in early 2023. Sunday work may also occur.
Ground monitoring is ongoing along the tunnel alignment and is done from both inside MudHoney and on the surface.
East Ballard
Crews prepared the base for the mechanical and electrical vault on NW 45th St to provide a stable surface to work on. Construction of the reinforced concrete structure will begin later this month.
You should anticipate:
- Starting in mid-June, one-lane closure on 11th Ave NW through November 2022. Flaggers will direct northbound and southbound traffic, and directional signage will be in place.
- Heavy equipment in the area
- NW 45th St closed to traffic; vehicles must detour onto NW 46th St
- Burke-Gilman Trail users remain detoured to the north side of NW 45th St
- Flaggers will help direct traffic during daytime working hours. Please follow all detour guidance on site. For safety, bicyclists should either dismount or cross train tracks at a 90-degree angle. Please use extra caution in wet weather as ramps may be slippery.
- Noise and vibrations typical of a construction site
Regular work hours will be Monday through Friday, from 7 am to 5 pm. Night and weekend work may occur.
Fremont
Lane reductions on Leary Way NW, between 1st Ave NW and NW 39th St, for utility work was completed in late-May. This month, utility work will begin within the east end of the site on 2nd Ave NW. Crews also continue to work on large eight-foot conveyance tunnel pipes underneath white tents within the site from 7 am to 10 pm on weekdays, and possibly 9 am to 10 pm on weekends, over the next few months.
During this time, you should anticipate:
- Dust and grinding noise
- Excavators working on-site for utility installation work
- Truck traffic on Leary Way NW as trucks bring and remove materials to and from the site
- NW 36th St between Leary Way NW and 3rd Ave NW closed (through the remainder of the project)
- Pedestrian detours on Leary Way NW; please follow all detour guidance on site
- Generators running during work hours to power equipment
- 2nd Ave NW, between Leary Way NW and NW Canal St, closed to vehicle and pedestrian traffic for sewer and diversion structure work at least through the end of 2022
- NW Canal St open to two-way traffic to allow access during this closure. Please do not park at the west end of NW Canal St so two-way traffic may turn around at the closure.
- Noise and vibrations typical of a construction site
Regular work hours will be Monday through Friday, from 7 am to 5 pm. Work on the large pipes inside the tents may occur during nights and weekends as described above.
Wallingford
Good news, the Wallingford Conveyance project began the public bidding process late last month, taking us one step closer to bringing in contractors and completing this project. You can find more information about this project on our website and we’ll have more details about the impacts once the contractor is on board.
In the meantime, crews continue working on the Wallingford shaft walls. Another large concrete pour is expected mid-June for the upper portion of the shaft walls.
During this time, you should anticipate:
- Concrete trucks coming in and out of the site
- Noise and vibrations typical of a construction site
Regular work hours will be Monday through Friday, from 7 am to 5 pm.
Queen Anne
Construction of underground vaults is ongoing through the summer. This work requires a slight adjustment to the Ship Canal Trail detour. The current Ship Canal Trail detour that has been in place for the past two years (near Ewing Park and adjacent to Seattle Pacific University) has been temporarily removed. The trail has been moved back near its original location for the summer of 2022. Our contractor will be working on both sides of the trail so please continue to remain alert when moving through this area.
During this time, you should anticipate:
- Trucks coming in and out of the site
- Noise and vibrations typical of a construction site
- The West Ewing Mini Park parking lot to remain closed through mid-2023
- A localized Ship Canal Trail detour at least through summer 2023 (see map). The trail has temporarily been adjusted for construction of the third below-grade vault through summer 2022 and will revert back to the detour shown in the linked map this fall.
Regular work hours will be Monday through Friday, from 7 am to 5 pm. Night and weekend work may occur.
|