Ship Canal Water Quality project update 12/22/21

Seattle Public Utilities and King County logos - white
Ship Canal logo

See you in 2022!

We’ll see you in the new year with more feature stories and neighborhood updates. As always, we encourage you to check out our Flickr albums with recent construction photos, including images of our new tunnel.


Ballard & MudHoney

MudHoney continues to be on a planned pause for trailing gear installation and will resume tunneling activities early next year.

When tunneling starts again, you should anticipate:

  • Truck deliveries of concrete segments and MudHoney equipment
  • Tunneling activities
  • Nighttime segment deliveries and tunnel spoils getting hauled off
  • Noise and vibrations typical of a construction site

Crews are working 24 hours a day, 5 days a week, and will continue until MudHoney reaches Wallingford in late 2022. Weekend work may also occur.

Crews will not be working on Friday, December 24 and Friday, December 31.

Ground monitoring is ongoing along the tunnel alignment and is done from both inside MudHoney and on the surface.


East Ballard

Through the end of the year, crews will be excavating for the mechanical and electrical vault on NW 45th St.

During this time, you should anticipate:

  • Heavy equipment in the area
  • NW 45th St closed to traffic; vehicles must detour onto NW 46th St
  • Burke-Gilman Trail users remain detoured to the north side of NW 45th St
  • Flaggers will help direct traffic during daytime working hours. Please follow all detour guidance on site. For safety, bicyclists should either dismount or cross train tracks at a 90-degree angle. Please use extra caution in wet weather as ramps may be slippery.
  • Noise and vibrations typical of a construction site

Regular work hours will be from 7 am to 5 pm Monday through Friday. Night and weekend work may occur. Crews will not be working on Friday, December 24 and Friday, December 31.


Fremont

Crews started jet grouting work in Leary Way NW in November. This work includes lane reductions on Leary Way NW, between 1st Ave NW and NW 39th St, with an optional detour. Jet grouting will continue through February. Work on the 8-ft conveyance tunnel will resume next year after jet grouting is complete.

During this time, you should anticipate:

  • Lane reductions on Leary Way NW December through approximately Feb. 2022 (see map with optional detour). We will continue to look for opportunities to open up the lanes whenever possible.
  • Excavators working on site for utility installation work
  • Truck traffic on Leary Way NW as trucks bring and remove materials to and from the site
  • NW 36th St between Leary Way NW and 3rd Ave NW closed (through remainder of the project)
  • Pedestrian detours on Leary Way NW, please follow all detour guidance on site
  • Generator running during work hours to power equipment
  • 2nd Ave NW, between Leary Way NW and NW Canal St, closed to vehicle and pedestrian traffic for sewer and diversion structure work at least through the end of the year
  • NW Canal St will be open to two-way traffic to allow access during this closure. Please do not park at the west end of NW Canal St to allow two-way traffic to turn around at the closure.
  • Noise and vibrations typical of a construction site

Regular work hours will be from 7 am to 5 pm Monday through Friday. Night and weekend work may occur. Crews will not be working on Friday, December 24 and Friday, December 31.


Wallingford

Crews continue working inside the shaft.

During this work, you should anticipate:

  • Trucks coming in and out of the site to deliver reinforcing steel and concrete
  • Noise and vibrations typical of a construction site

Regular work hours will be from 7 am to 5 pm Monday through Friday. Crews will not be working on Friday, December 24 and Friday, December 31.


Queen Anne

Crews will continue excavating diversion structures for the conveyance pipe.

During this time, you should anticipate:

  • Trucks coming in and out of the site
  • Noise and vibrations typical of a construction site
  • The West Ewing Mini Park parking lot to remain closed through mid-2023
  • A localized Ship Canal Trail detour through summer 2022 (see map)

Regular work hours will be from 7 am to 5 pm Monday through Friday. Night and weekend work may occur. Crews will not be working on Friday, December 24 and Friday, December 31.


Contact us

Please email SPU_ShipCanalProject@seattle.gov with questions or comments or call our hotline at (206) 701-0233. You can also find information online at spushipcanal.participate.online/.To support the community during active tunneling, we have changed our hotline hours to 24 hours a day, Monday through Friday.


Have you signed up for AlertSeattle?

Alert Seattle Logo

AlertSeattle is the official emergency notification system used by the City of Seattle to communicate with city residents during emergencies. Sign up now to receive free alerts from the City via text message, email, voice message or social media.

  • To sign-up for AlertSeattle, click here
  • To update your existing AlertSeattle preferences, click here to access your account

Click here for more information