Daily Project Update - 76th Street Sewer Project


  • Today: The contractor is compacting and fine grading driveway and ramp slopes along the project length in preparation for tomorrow’s paving of the walkway on the east side of 76th Ave. Contractor has also laid out locations of asphalt thickened edge and additional approach paving on the west side of the road with CEMEX. The contractor is also re-adjusting structures in the walkway to finish grade. 
76th 7-2-14

Information on the schedule for the road repair and final street paving work for the 76th Street Sewer Project.

The most current schedule information available is as follows (subject to weather conditions):

  •    7/3: Pathway Paving
  •    7/7 week: Move out, remove traffic signs, etc.

The city is committed to keeping you informed on the remainder of this project and will be sending out daily updates (Monday thru Friday).

Please see our website for more information, pictures and updates.