City of Lynnwood Project Update - 2025 Paving Program - October 3, 2025

Lynnwood Washington

2025 Paving Program

Alderwood Mall Parkway – from Alderwood Mall Boulevard to 184th St SW

33rd Ave W – from upcoming Poplar Bridge project to 184th St SW


Crews pouring concrete curb and gutter.

Crews pouring concrete curb and gutter on 188th St SW, east of 33rd Ave W.


Please follow all pedestrian and traffic control.

Weeks ending October 3rd and 14th:

  • Week ending Oct. 3rd: There will be night work on Alderwood Mall Pkwy to pour concrete curbs and grind the roadway. 
  • Oct. 5th - 6th (night shift): Final paving on 33rd Ave. W.
  • Oct. 7th - 10th (day shift): The crews will be raising utilities and installing traffic loops (detectors) on 33rd Ave. W.
  • Oct. 7th - 9th (night shift): The crews will be paving Alderwood Mall Pkwy and installing traffic loops (detectors)
  • Oct. 13th - 14th: Final utility adjustments in the roadway on both Alderwood Mall Pkwy (night shift) and 33rd Ave. W. (day shift)
  • The project will go into suspension after this work is completed to allow for the asphalt cure time of 21 days. After the cure time, the final roadway channelization will proceed.

Questions during construction? Contact us:

Michael Whaley, Senior Project Manager

email: mwhaley@LynnwoodWA.gov

phone: 425-670-5214