Crews pouring concrete curb and gutter on 188th St SW, east of 33rd Ave W.
Please follow all pedestrian and traffic control.
Weeks ending October 3rd and 14th:
- Week ending Oct. 3rd: There will be night work on Alderwood Mall Pkwy to pour concrete curbs and grind the roadway.
- Oct. 5th - 6th (night shift): Final paving on 33rd Ave. W.
- Oct. 7th - 10th (day shift): The crews will be raising utilities and installing traffic loops (detectors) on 33rd Ave. W.
- Oct. 7th - 9th (night shift): The crews will be paving Alderwood Mall Pkwy and installing traffic loops (detectors)
- Oct. 13th - 14th: Final utility adjustments in the roadway on both Alderwood Mall Pkwy (night shift) and 33rd Ave. W. (day shift)
- The project will go into suspension after this work is completed to allow for the asphalt cure time of 21 days. After the cure time, the final roadway channelization will proceed.
Questions during construction? Contact us:
Michael Whaley, Senior Project Manager
email: mwhaley@LynnwoodWA.gov
phone: 425-670-5214
For more information on this project visit the project website.