Crews forming curbs, gutters & sidewalks at the intersection of 76th Ave W & 204th St SW and in the College Place Elementary parking lot.
The City of Lynnwood has begun construction to pave the gravel segment of 204th St SW from 76th Ave W east to the segment that is currently paved.
This project includes construction of pedestrian improvements adjacent to the College Place Schools.
Please follow all pedestrian and traffic control.
August 12 - 23, 2024
- Crews have completed underground utility work at the intersection of 204th St SW & 76th Ave W.
- Crews have begun installing concrete curb and gutter and sidewalks at the intersection of 204th St SW & 76th Ave W and in the parking lot of College Place Elementary parking lot.
August 26 - September 6, 2024
- Crews are working on grading the roadway in preparation for paving.
- Paving is anticipated to begin August 27th - 30th. Please expect traffic delays on 76th Ave W during paving operations.