Crews installing catch basins for the storm system on 204th St SW
The City of Lynnwood has begun construction to pave the gravel segment of 204th St SW from 76th Ave W east to the segment that is currently paved.
This project includes construction of pedestrian improvements adjacent to the College Place Schools.
Please follow all pedestrian and traffic control.
July 29 - August 9, 2024
- Crews have completed the installation of the CMP (Corrugated Metal Pipe) Stormwater Detention Facility on 204th St SW.
- Work has begun to install other related catch basins for the storm system.
- Sidewalk and curb ramp work on the east and west sides of 76th Ave W near 204th St SW has begun.
August 12 - 23, 2024
- Crew will begin installing electrical conduit across 76th Ave W for the new signal system.
- Work will continue on the storm system, sidewalk and ramps.
For more information on this project visit the project website.
Title VI Non-Discrimination Information
|