Placing bench in Scriber Creek Park
Please follow all pedestrian and traffic control.
Week of November 13, 2023
- Continue placement of boardwalk railings
- Continue placement of FRP beams boardwalk #3
- Continue placement of decking boardwalk #3
- Preparing for Signal Cabinet foundation placement SE corner 200th St SW and Cedar Valley RD
- Place picnic tables, benches and trash receptacles in Scriber Creek Park
- Place Bark throughout the site
Week of November 20, 2023
- November 23 & 24 Holiday observed, No work to be performed
- Continue placement of boardwalk railings
- Place Bark throughout the site
- Place picnic tables, benches and trash receptacles in Scriber Creek Park
Questions during construction? Contact us:
David Meisenheimer - Construction Project Manager
email: David.Meisenheimer@psomas.com
phone: 206-369-3043
Webpage: www.LynnwoodWA.gov/ScriberCreekTrail