City of Lynnwood Project Update - 2023 Pavement Program - August 18, 2023

Lynnwood Washington

2023 Paving Program

Crews paving the intersection of 168th St SW and 52nd Ave W

Crews paving the intersection of 168th St SW and 52nd Ave W


Please follow all traffic control direction.


Week Ending August 18, 2023

Multiple Sites - Please refer to the site map below

  • Crews completed paving at Site #2 - 168th St SW and 52nd Ave W - Thank you for your patience during the road closures for this portion of the project.

Week of August 21, 2023

  • Crews will be returning to complete ramps and other items at various sites.
  • Once sites that were begun are completed, crews will begin the next phase of the Paving Program at Site #1. This site is along 68th Ave W from 204th St SW to 208th St SW.

You should expect traffic delays in these areas.


2023 Paving Program Sites Map

2023 Pavement Program Sites Map


For more information on this project visit the project website.  And follow us on Twitter @LynnwoodStreets.


Title VI Non-Discrimination Information