Driving piles for Boardwalk #2
Please follow all pedestrian and traffic control.
Week of July 31, 2023
- Begin Driving piles for Boardwalk #2
- Prepare for placement of piles for Boardwalk #3
- Mobilize pile driver to Boardwalk #3
- Begin placement of piles for Boardwalk #3
Week of August 7, 2023
- Continue placement of piles for Boardwalk #3
- Remove tree at 48th Ave W
- Begin forming and placement of rebar for pile caps for Boardwalk #2
- Place Handrail on Boardwalk #1
Questions during construction? Contact us:
David Meisenheimer - Construction Project Manager
email: David.Meisenheimer@psomas.com
phone: 206-369-3043
Webpage: www.LynnwoodWA.gov/ScriberCreekTrail
Title VI Non-Discrimination Information
For more information on this project, visit the project website and follow us on Twitter @LynnwoodStreets.
|