City of Lynnwood Project Update - Scriber Creek Trail Improvement Project - August 4, 2023

Lynnwood Washington

Scriber Creek Trail Improvement


Driving piles for Boardwalk #2

Driving piles for Boardwalk #2


Please follow all pedestrian and traffic control.

Week of July 31, 2023

  • Begin Driving piles for Boardwalk #2
  • Prepare for placement of piles for Boardwalk #3
  • Mobilize pile driver to Boardwalk #3 
  • Begin placement of piles for Boardwalk #3 

Week of August 7, 2023

  • Continue placement of piles for Boardwalk #3
  • Remove tree at 48th Ave W
  • Begin forming and placement of rebar for pile caps for Boardwalk #2
  • Place Handrail on Boardwalk #1