City of Lynnwood Project Update - Scriber Creek Trail Improvement Project - July 14, 2023

Lynnwood Washington

Scriber Creek Trail Improvement


The asphalt has been removed along the area of boardwalk #3.

The asphalt has been removed along the area of boardwalk #3.


Please follow all pedestrian and traffic control.

Week of July 10, 2023

  • Began clearing for Boardwalk #3
  • Prep for placement of piles for Boardwalk #2

Week of July 17, 2023

  • Continue clearing and building access into the wetland for Boardwalk #3
  • Prepare for placement of piles for Boardwalk #2 and #3

Questions during construction? Contact us:

David Meisenheimer - Construction Project Manager

email: David.Meisenheimer@psomas.com

phone: 206-369-3043

Webpage:  www.LynnwoodWA.gov/ScriberCreekTrail


Title VI Non-Discrimination Information


For more information on this project, visit the project website and follow us on Twitter @LynnwoodStreets.