City of Lynnwood Project Update - 2023 Pavement Program - June 23, 2023

Lynnwood Washington

2023 Paving Program

Crews Install ADA Ramps at Site 6 near 46th Ave W and 192nd St SW

Crews install ADA Ramps at Site 6 near 46th Ave W and 192nd St SW


Please follow all traffic control direction.


Week Ending June 23, 2023

Multiple Sites - Please refer to the site map below

  • Water service replacements are underway at Site 4
  • ADA curb ramp have been poured at:
    • Site 4 - 182th St SW, 183rd St SW between 60th Ave W and 64th Ave W
    • Site 6 - 49th Ave W and 192nd St SW
    • Site 7 - 43rd PL W and 41st Ave W off of 188th St SW
  • Paving has been completed at Sites 3 and 7
  • Paving is anticipated at Site 6 week of June 26th.

The City and the Crews appreciate the communities patience during construction! 


For more information regarding the 2023 Paving Program please visit the webpage at

www.LynnwoodWA.gov/2023Paving

2023 Paving Program Sites Map

2023 Pavement Program Sites Map

For more information on this project visit the project website.  And follow us on Twitter @LynnwoodStreets.


Title VI Non-Discrimination Information