Crews install ADA Ramps at Site 6 near 46th Ave W and 192nd St SW
Please follow all traffic control direction.
Week Ending June 23, 2023
Multiple Sites - Please refer to the site map below
- Water service replacements are underway at Site 4
- ADA curb ramp have been poured at:
- Site 4 - 182th St SW, 183rd St SW between 60th Ave W and 64th Ave W
- Site 6 - 49th Ave W and 192nd St SW
- Site 7 - 43rd PL W and 41st Ave W off of 188th St SW
- Paving has been completed at Sites 3 and 7
- Paving is anticipated at Site 6 week of June 26th.
The City and the Crews appreciate the communities patience during construction!
For more information regarding the 2023 Paving Program please visit the webpage at
www.LynnwoodWA.gov/2023Paving
 2023 Pavement Program Sites Map
For more information on this project visit the project website. And follow us on Twitter @LynnwoodStreets.
Title VI Non-Discrimination Information
|