Sprague Park parking lot being paved.
200TH ST SW SCHEDULED TO OPEN LATE TODAY, MAY 26TH!
Thank you to our project neighbors and our traveling community for your patience while the Scriber Creek Trail Phase 2 project has had 200th St SW closed.
Having this street closure allowed work to be completed in a safe environment and assisted in the work being completed sooner than if the road had remained open.
Please note there maybe intermittent road closures as the project continues.
Please follow all pedestrian and traffic control.
Weeks of May 22, 2023 and May 29, 2023
Week of May 22, 2023
- Begin placement of concrete walkway and pedestrian railing Boardwalk #1
- Continue grading for placement of asphalt on 200th St SW
- Continued grading of Sprague Park parking lot
- Place asphalt paving in Sprague Park parking lot and on south side of 200th St SW
- Open 200th St SW on May 26th!
Week of May 29, 2023
- May 29, no work in observance of Memorial Day
- Placement of signal pole foundations at the SE and NE corners of 200th St SW and Cedar Valley Rd
- Place concrete on hollowcore for Boardwalk #1
- Grading SW corner at 200th St SW and Cedar Valley RD
Questions during construction? Contact us:
David Meisenheimer - Construction Project Manager
email: David.Meisenheimer@psomas.com
phone: 206-369-3043
Webpage: www.LynnwoodWA.gov/ScriberCreekTrail
Title VI Non-Discrimination Information
For more information on this project, visit the project website and follow us on Twitter @LynnwoodStreets.
|