City of Lynnwood Project Update - Scriber Creek Trail Improvement Project - April 7, 2023

Lynnwood Washington

Scriber Creek Trail Improvement


Forming a pile cap for boardwalk #1 along 200th St SW

Forming a pile cap for boardwalk #1 along 200th St SW


ROAD CLOSURE

  • January 3, 2023 through Late April, 2023
    • 200th Ave W between Cedar Valley Rd and 52nd Ave W

Please follow all traffic signage for detour routes


Please follow all pedestrian and traffic control.


Weeks of April 3, 2023 and April 10, 2023

Week of April 3, 2023

  • Placement of rebar and forms for pile caps
  • Signal and illumination conduit placed on SE corner Cedar Valley RD and 200th St SW
  • Placement of curb and gutter at SE corner of Cedar Valley mid-block crossing

Week of April 10, 2023

  • Placement of concrete pile caps Boardwalk #1
  • Begin placement of drainage on 200th St SW
  • Placement of sidewalk SE corner Cedar Valley Rd

Questions during construction? Contact us:

David Meisenheimer - Construction Project Manager

email: davidm@kpg.com

phone: 206-369-3043

Webpage:  www.LynnwoodWA.gov/ScriberCreekTrail


Title VI Non-Discrimination Information


For more information on this project, visit the project website and follow us on Twitter @LynnwoodStreets.