City of Lynnwood Project Update - Scriber Creek Trail Improvement Project - January 27, 2023

Lynnwood Washington

Scriber Creek Trail Improvement


Crews installing stormwater bypass along 200th St SW

Crews installing stormwater bypass along 200th St SW


ROAD CLOSURE

  • January 3, 2023 through Late April, 2023
    • 200th Ave W between Cedar Valley Rd and 52nd Ave W

Please follow all traffic signage for detour routes


Please follow all pedestrian and traffic control.


Weeks of January 23, 2023 And January 30, 2023

Week of January 23, 2023

  • Continue placement of silt fencing and construction fencing
  • Removal of old water main and utilities for pile placement
  • Placing temporary bypass for stormwater

Week of January 30, 2023

  • Continue clearing and grubbing in Scriber Creek Park
  • Continue placement of silt fencing and construction fencing
  • Begin installation of illumination and signal conduits
  • Install habitat logs in Scriber Creek Park

Questions during construction? Contact us:

David Meisenheimer - Construction Project Manager

email: davidm@kpg.com

phone: 206-369-3043

Webpage:  www.LynnwoodWA.gov/ScriberCreekTrail