City of Lynnwood Project Update - Scriber Creek Trail Improvement Project - December 16, 2022

Lynnwood Washington

Scriber Creek Trail Improvement


Crews installing a silt fence along 200th St SW along Sprague's Pond

Crews installing a silt fence at 200th St SW along Sprague's Pond


Upcoming Road Closure

  • January 3, 2023 through Late April, 2023
    • 200th Ave W between Cedar Valley Rd and 52nd Ave W

Please follow all traffic signage for detour routes

Detour Route for 200th Ave W - Cedar Valley Rd to 52nd Ave W Closure

Please follow all pedestrian and traffic control.


Weeks of December 12, 2022 and December 19, 2022

Work is weather permitting

Week of December 12, 2022

  • Work began December 12, 2023
  • Began clearing and grubbing south side on 200th ST SW
  • Placement of silt fencing and slope protection on south side of 200th ST SW
  • Potholing of utilities to occur this week as well

Week of December 19, 2022

  • The above to continue into this week weather permitting

Week of December 26, 2022

  • Crews off for the holiday’s, no work to be performed

Questions during construction? Contact us:

David Meisenheimer - Construction Project Manager

email: davidm@kpg.com

phone: 206-369-3043

Webpage:  www.LynnwoodWA.gov/ScriberCreekTrail


Title VI Non-Discrimination Information


For more information on this project, visit the project website and follow us on Twitter @LynnwoodStreets.