|
Road Excavation resumes between 40th and 36th
Upcoming road closures
-
December 15th - 9 p.m. to 5 a.m.
- I-5 South Bound - Exit 181 to West Bound 196th (SR 524) will be closed
-
December 20 at 8 a.m. through December 21 at 5 p.m.
- 40th Ave W at 196th St SW will be fully closed from Tuesday, December 20 at 8 a.m. through Wednesday, December 21 at 5 p.m. for traffic signal installation.
- Please follow all traffic signage for detour routes
Concrete work continues
As part of this project, crews will continue completing sidewalk, driveway, and street upgrades which includes pouring and curing concrete. All concrete work is weather dependent, and the schedule subject to change if there is cold or wet weather in the forecast.
Access in and out of driveways will be maintained to the extent possible. If driveways need to be closed for upgrades, our team will notify individual properties in advance.
We appreciate your patience as crews work toward completing this project.
We understand that the 196th St Improvement Project is impactful on the surrounding neighbors and traffic. Major roadway work for this project is expected to be finished in late 2023.
Our crews are working to complete upgrades as efficiently and effectively as possible. We will continue shifting travel lanes around work zones to allow us to maintain the safety of the crews and traveling public.
Please follow all pedestrian and traffic control.
Weeks of December 5, 2022 and December 12, 2022
48th Ave W to 36th Ave W
- Installing retaining walls
- Roadway excavation
- Grading and placing sidewalk concrete
- Grading and paving driveways and curbs
- Drainage installation
- Placing lighting along the corridor
- Installing signals
- Crews install curbs at the median
Other areas of work
- Equipment and materials will be staged along 195th Pl SW for the duration of the project
Questions during construction? Contact us:
Email: 196street@LynnwoodWA.gov
Construction hotline: 425-224-2440
Webpage: www.LynnwoodWA.gov/196street
Title VI Non-Discrimination Information
For more information on this project, visit the project website and follow us on Twitter @LynnwoodStreets.
|