Crews prepare the center of 196th St SW for the installation of a new concrete median
Upcoming road closures at 40th Ave W
Thank you for your patience while crews have been completing upgrades to the traffic signal at 44th Ave W. In the coming weeks, crews will install a new traffic signal at 40th Ave W, and travelers can expect closures and detours at that time. Specific dates for this closure will be shared soon.
Construction during winter weather
Crews are unable to complete a full week of work this week due to inclement weather. Low temperatures, wet weather, and frozen ground create poor conditions for excavation and concrete pouring. Crews are working to complete upgrades efficiently and will continue work as soon as possible.
Concrete work continues
As part of this project, crews will continue completing sidewalk, driveway, and street upgrades which includes pouring and curing concrete. All concrete work is weather dependent, and the schedule subject to change if there is cold or wet weather in the forecast.
Access in and out of driveways will be maintained to the extent possible. If driveways need to be closed for upgrades, our team will notify individual properties in advance.
We appreciate your patience as crews work toward completing this project.
We understand that the 196th St Improvement Project is impactful on the surrounding neighbors and traffic. Major roadway work for this project is expected to be finished in late 2023.
Our crews are working to complete upgrades as efficiently and effectively as possible. We will continue shifting travel lanes around work zones to allow us to maintain the safety of the crews and traveling public.
Please follow all pedestrian and traffic control.
Weeks of November 28, 2022, and December 5, 2022
Due to poor weather conditions, crews are unable to work a full week this week. When work resumes, activities will include the following:
48th Ave W to 36th Ave W
- Installing retaining walls
- Roadway excavation
- Grading and placing sidewalk concrete
- Grading and paving driveways and curbs
- Drainage installation
- Placing lighting along the corridor
- Installing signals
- Crews install curbs at the median
Other areas of work
- Equipment and materials will be staged along 195th Pl SW for the duration of the project
Questions during construction? Contact us:
Email: 196street@LynnwoodWA.gov
Construction hotline: 425-224-2440
Webpage: www.LynnwoodWA.gov/196street