2022 Pavement Preservation Project


Crews raise utilities along 176th ST SW

Crews raise utilities along 176th ST SW


Please follow all traffic control direction.


Week Ending October 14, 2022

176th St SW Between 44th Ave W and Hwy 99

  • Paving has been completed on 176th St SW between 44th Ave W and 52nd Ave W.
  • Crews will be completing the work of raising utilities to roadway grade.
  • There will be limited traffic delays during this work.
  • Work will be suspended while the contractor waits for new signal heads to be received from the manufacturer. These are anticipated to arrive mid November.

The City and the Crews appreciate the communities patience during construction! 


Paving dates are subject to weather and may change.


For more information on this project visit the project website.  And follow us on Twitter @LynnwoodStreets.