City of Lynnwood Project Update - 196th ST SW (SR 524) Improvement Project - September 7, 2022

Lynnwood Washington

196th St SW (SR 524) Improvement Project


Crews pave driveways near 44th Ave W and 196th St SW

Crews pave driveways near 44th Ave W and 196th St SW


We understand that the 196th St Improvement Project is impactful on the surrounding neighbors and traffic. Major roadway work for this project is expected to be finished in late 2023.

This schedule may change depending on weather conditions or availability of materials.

We thank you for your patience during construction. Our crews are working to complete upgrades as efficiently and effectively as possible. We will continue shifting travel lanes around work zones to allow us to maintain the safety of the crews and traveling public. 

Please follow all pedestrian and traffic control.


Weeks of September 5, 2022 and September 12, 2022 

48th Ave W to 36th Ave W

  • Installing drainage and retaining walls
  • Grading and placing sidewalk concrete
  • Grading and paving driveways and curbs
  • Converting overhead utilities to underground
  • Digging (potholing) to confirm underground utility locations
  • Placing lighting along the corridor
  • Roadway excavation
  • Property restoration

Other areas of work

  • Equipment and materials will be staged along 195th Pl SW for the duration of the project

Questions during construction? Contact us:

Email: 196street@LynnwoodWA.gov

Construction hotline: 425-224-2440

Webpage: www.LynnwoodWA.gov/196street


Title VI Non-Discrimination Information


For more information on this project, visit the project website and follow us on Twitter @LynnwoodStreets.